Project schedule

The schedule is the project tab where you plan tasks and milestones and track their progress and dependencies. The schedule has three views:

Schedule items:

  • task – a circle icon next to the name,
  • milestone – a diamond icon next to the name; it marks an important moment in the project, for example the end of a phase,
  • summary task – a task with subtasks, with a bold name and a subtask counter.

The schedule can be changed by:

  • people with the Admin level in the Schedule module (see Project permissions),
  • owners of tasks and milestones, within the scope made available to owners (see Project permissions).

Adding schedule items

Adding a task

  1. Click New task above the list. A name field appears.
  2. Type the name and press Enter. The task appears on the list with a circle icon next to the name.

Adding a milestone

  1. Click the arrow next to New task and choose New milestone.
  2. Type the name and press Enter. The milestone appears with a diamond icon next to the name.

Schedule list with the New task button and the New milestone option highlighted

A milestone has no duration, so only its end date is set (see Task start and end date). It can be done or not done. You can change the item type later (see Changing the schedule item type).

A new item goes to the end of the list, unless a row is selected. To insert an item in a chosen place, see Schedule structure.

Schedule structure (WBS)

The WBS number shows the position of an item in the structure. An item placed under another item is its subtask, and the parent item becomes a summary task.

On the schedule list, you can:

  • add an item in a chosen place,
  • change the level of an item in the structure,
  • change the order of items.

Adding an item in a chosen place

You can add an item in two ways.

Method 1: the New task button

  1. Select a row by clicking its number at the beginning of the row.
  2. Click New task above the list (or the arrow next to it and New milestone). The new item appears below the selected row.

Method 2: the item menu

  1. Hover over the item and click the three-dot icon next to the name.
  2. Choose Add task or Add Milestone, and then:
    • Above – the new item appears above the chosen one,
    • Below – the new item appears below the chosen one,
    • Subtask – the new item becomes a subtask of the chosen one.

Schedule list with two ways to add an item: 1 - the selected row and the New task button, 2 - the three-dot menu with the Add task item and the Above, Below, Subtask submenu; they are highlighted in red

Changing the level and order

  1. Click the three-dot icon next to the item name and choose Change level.
  2. Choose:
    • Move down – the item becomes a subtask of the item above it,
    • Move up – the item moves up one level,
    • Move above or Move below – the item moves before the previous item or after the next item at the same level.

You can also drag an item by the six-dot handle on the left side of the row, next to the WBS column.

Important: Summary tasks are moved together with their subtasks.

Summary task

A summary task is a task that has subtasks. It appears when you add a subtask under a task or when you move down an item that is below it. On the list, it is distinguished by a bold name and a subtask counter.

Most values of a summary task come from its subtasks:

  • Dates – the start date is the earliest start of the subtasks, and the end date is the latest end. Duration is the number of working days between them.
  • Progress – the average progress of the subtasks, weighted by their duration. When all subtasks are done, the summary task is also done.
  • Allocation – a summary task has its own allocation. In the Allocation column, the list shows the sum with the subtasks, and the own value in brackets.
  • Owner – has owner rights to all subtasks (see Owners).

Changes to a summary task carry over to its subtasks:

  • changing the start date moves all subtasks by the same number of working days,
  • marking a summary task as done (with the status icon next to the name) completes all subtasks.

The summary task panel has a Subtasks section with the list of direct subtasks. Click a name to open the subtask, and click Add subtask to add a new one.

A summary task can be cloned alone or together with its subtasks (see Cloning an item).

Warning: Deleting a summary task also deletes all its subtasks.

Changing the schedule item type

A task can be changed into a milestone and the other way round.

  1. Click the three-dot icon next to the item name, or in the top right corner of the item panel.
  2. Choose Change to milestone or Change to task.
  3. If the item has a baseline, click Confirm.

Item menu in the schedule list with the Change to milestone option highlighted

Effects of the change:

  • a task changed into a milestone keeps its end date, and progress other than 100% changes to 0%,
  • a milestone changed into a task becomes a one-day task.

Warning: Changing the type removes the allocation assigned to owners and the baseline planned dates of the item.

Task start and end date

Task dates are set in the Start, End and Duration columns on the list or in the task panel. Duration is counted in project working days (see Working days and holidays). The end date and duration of a summary task come from its subtasks (see Schedule structure).

Changing dates

  1. Click the Start or End field in the task row or in the task panel. A calendar with the project working days opens.
  2. Choose a day. The other values are recalculated automatically.

Enter the duration in the Duration field as a number of working days.

How dates are recalculated:

  • changing the start date moves the task, and the duration stays the same,
  • changing the end date or the duration lengthens or shortens the task,
  • the dates of a task with dependencies may be recalculated according to its predecessors. The system then displays the message: Dates have been updated from relations.

Working days and holidays in the schedule

Every project has its own working days and holidays. A new project has working days from Monday to Friday. Task dates and durations depend on these settings.

Important: Schedule dates depend only on the working days and holidays of the project. The days off of the organization affect the availability of resources (see Resources in the organization).

Changing working days

  1. Click Settings above the list and choose Working days. The Working days window opens.
  2. Select the working days of the week. At least one day must stay selected.
  3. To add a holiday, click Add holiday and enter the name and the date.
  4. Click Save. Task dates are recalculated and the page refreshes.

Schedule with the Settings button and the open Working days window with the weekday buttons and the list of days off; the button and the window are highlighted in red

Tasks that started on a day off move to the nearest working day. Their duration stays the same.

Warning: A change of working days cannot be undone. After it is saved, earlier schedule changes cannot be undone either (see Undoing schedule changes).

Dependencies between schedule items

A dependency links two items: a predecessor and a successor. The dates of the successor result from the dates of the predecessor. You can also draw dependencies on the Gantt chart (see Project Gantt).

Types of dependencies:

  • End – Start – the successor starts after the predecessor ends,
  • Start – Start – the successor starts together with the predecessor,
  • End – End – the successor ends together with the predecessor,
  • Start – End – the successor ends when the predecessor starts.

Fixed lag is the gap in working days between the items. It is turned on by default and equals 0. When you turn it off, the successor can start later than the dependency implies.

Adding a dependency

  1. Click the three-dot icon next to the item name and choose Add dependency.
  2. Choose an item from this project or from another project and click Next.
  3. In the From: field, choose the predecessor.
  4. Choose the Dependency type and set the Fixed lag.
  5. Click Save. The dates of the successor are recalculated.

Schedule list with the three-dot menu of a task expanded; the menu icon and the Add dependency item are highlighted in red
Add dependency window with the From and To items, the dependency type and the fixed lag highlighted

Dependencies are visible in the item panel in the Depends on: and Affects: sections. The pencil icon next to a dependency opens the Edit dependency window, where you change the type, the lag and the direction, or delete the dependency.

Rules:

  • dependencies with items of other projects are recalculated only in the project program,
  • dependencies cannot form loops,
  • there can be only one dependency between two items.

Schedule item owners

An item can have several owners. In addition, a task can be assigned directly to a department. An owner sees the assigned tasks in the Tasks module. The scope of what an owner can change is set in the project permissions (see Project permissions).

Assigning an owner

  1. Click the Owner field in the item row or in the item panel.
  2. Choose a person from the list. Add more people the same way.

A department is assigned the same way, in the Department field (turn on the column with the Columns button).

Effects of the assignment:

  • assigning an owner adds the owner’s department to the item,
  • a new owner is added to the project and gets a notification,
  • a removed owner disappears from the project if they have no other items or permissions in it.

Owners of many items at once are changed in bulk edit (see Bulk edit).

Task progress

Progress is the percentage of task completion. A task is done at 100%.

Changing progress

  1. Click the progress bar in the task row or the progress field in the task panel.
  2. Type a value from 0 to 100 and press Enter.

Clicking the status icon next to the name marks the item as done (100%) or not done (0%). This is how you change the progress of a milestone and a summary task (see Schedule structure).

Important: Clicking the status icon changes progress immediately, without confirmation. An accidental change can be undone (see Undoing schedule changes).

Effects:

  • when a task has predecessors that are not done, the system shows their list and asks for confirmation (the confirmation closes only the current item),
  • when all predecessors of a successor are done, its owners get a notification.

Progress can also be changed on the Gantt chart (see Project Gantt).

Editing a schedule item

Clicking an item name in any view opens a panel on the right. Every change is saved immediately.

The panel contains:

  • the name with the status icon,
  • dates and progress,
  • allocation and time tracking (when the Resources and Time tracking modules are turned on in the project),
  • owners and departments (see Schedule item owners),
  • dependencies (see Dependencies between schedule items) and the linked budget, risks and products,
  • schedule attributes (see Schedule attributes),
  • the description, attachments and subtasks,
  • the Comments and History tabs.

Schedule item details panel with the name, timeline and owners highlighted

The three-dot menu in the top right corner of the panel contains, among others, Add dependency, Clone (see Cloning a schedule item), Delete, Copy link and Change to milestone. The menu next to the name on the list also has Rename, Color and Show details.

Adding an attachment

  1. In the item panel, click the paperclip icon in the top right corner.
  2. Choose Files (a file from disk), Link or Add existing (a file from project files, see Project files).

Cloning a schedule item

Cloning creates a copy of an item below the original, with – copy added to the name.

Cloning an item

  1. Click the three-dot icon next to the item name.
  2. Choose Clone Task (for a milestone, Clone Milestone). The copy appears below the original.

In the item panel, the same option is called Clone. For a summary task, you can choose Clone task only or Clone with subtasks.

The copy contains the dates, progress, allocation, owners and departments, dependencies, description, attachments, schedule attributes and row color. The baseline, links to the budget, risks and products, logged time, comments and history are not copied.

The owners of the copy get a notification.

Bulk edit

Bulk edit changes many items at once.

  1. Select the checkbox next to the first item. The Bulk edit panel opens on the right.
  2. Select the other items. The checkbox in the first row selects all items.
  3. In the panel, set the new values. Leave the fields you do not change on Skip.
  4. Click Update selected.

Bulk edit panel with two selected items and the Update selected button highlighted

In the panel, you can change:

  • Owner,
  • Department,
  • Start, End and Duration – the dates are saved when all three fields are filled in,
  • schedule attributes,
  • Color.

Important: A new owner or department replaces the existing ones on all selected items.

The Delete selected button deletes the selected items together with their subtasks.

Schedule history

History records schedule changes: who changed what and when.

  • Schedule history – the History button above the list,
  • Item history – the History tab in the item panel.

Schedule with the History button and the open History of change panel with the list of changes from the newest; the button and the panel are highlighted in red

You can undo changes (see Undoing schedule changes).

Undoing schedule changes

Undoing restores the schedule to the state before the chosen change.

  1. Click History above the list (see Schedule history) or open the History tab in the item panel.
  2. Next to the chosen change, click Undo changes. The schedule immediately returns to the state before that change.

History of change panel with the Undo changes button highlighted

Warning: Undoing also cancels all later changes in the project.

Rules:

  • the last 25 changes in the project can be undone,
  • a person with the Admin level in the Schedule module can undo any change,
  • other users can undo only their own change, and only if nobody has changed the project since.

Warning: Changes of working days, schedule imports and changes to schedule attributes cannot be undone. After such an operation, earlier changes cannot be undone either.

Customizing the schedule list view

Each user customizes the list view for themselves: filters items, chooses columns and collapses groups of subtasks.

Filtering the list

The Filter button above the list opens the filter bar. You can narrow the list by:

  • a word in the Filter by name field,
  • status – done or not done,
  • type – tasks or milestones,
  • owner, including items without an owner,
  • department (when the organization has departments),
  • a range of start dates and end dates,
  • values of schedule attributes.

Choosing columns

  1. Click Columns above the list.
  2. Turn columns on or off with the switches.
  3. To change the order, drag a column by the six-dot symbol.

The available columns depend on the modules turned on in the project, for example Allocation, budget and baseline columns, and schedule attributes (see Schedule attributes in a project). The Name column is always visible. The column setting is saved in the browser, separately for each project.

The export contains the columns visible on the list (see Exporting the schedule list).

Collapsing and expanding rows

Groups of subtasks are collapsed and expanded with the arrows icon in the first row of the list, next to the project name. Clicking the icon opens a menu:

  • Expand all – all schedule items are visible,
  • Collapse all – only the project row is visible,
  • Expand to level 1, 2 and further – items down to the chosen WBS level are visible, and deeper ones are collapsed. For example, level 1 shows only the top-level items.

Zoomed fragment of the schedule list with the arrows icon next to the project name in the first row and the open menu: Expand all, Collapse all, Expand to level 1-5; the icon and the menu are highlighted in red

The number of levels in the menu depends on the depth of the structure (5 at most). A single group is collapsed with the arrow next to the name of the summary task.

Importing a schedule into an existing project

You can add items from a template, an Excel file or a Microsoft Project file to the schedule of an existing project. New items go to the end of the schedule. Import into a new project is described in Creating a project.

Warning: An import cannot be undone. After an import, earlier schedule changes cannot be undone either (see Undoing schedule changes).

To start an import, click Settings above the list and choose Import.

Settings menu of the schedule with the Import options From template, From Microsoft Excel and From Microsoft Project highlighted

Import from a template

  1. Choose From template and choose a template in the Project template field.
  2. Choose Start date of the template or End date of template and enter the date.
  3. Click Next, check the preview and click Add.

Important: Import from a template turns on in the project the schedule attributes used in the template.

Import from Microsoft Excel

  1. Choose From Microsoft Excel and select an .xlsx file.
  2. Click Next and assign the file columns to schedule fields (see Importing a project from Excel).
  3. Click Add.

Import from Microsoft Project

  1. Choose From Microsoft Project and select an .mpp file.
  2. Click Next and choose how dates are determined:
    • Recalculate dependencies (default) – dates result from dependencies and durations,
    • Keep dates – the dates from the file stay, and the dependencies get lags.
  3. Click Add.

The dates from the file adjust to the working days of the project. The changes are visible in the Data mapping step.

Exporting the schedule list

The schedule list can be downloaded as an Excel file or as an .xml file for Microsoft Project.

  1. Click Export above the list.
  2. Choose Microsoft Excel (.xlsx) or Microsoft Project (.xml). The file downloads automatically.

The file contains the columns visible on the list (see Customizing the schedule list view). The Gantt chart is exported separately (see Exporting the Gantt chart).