Resources in the project

Project resources are the working time of employees planned on tasks. For each task, you set the effort, and when the task has owners, the effort is split between them.

Based on this, the Resources tab in the project and the Gantt chart show how much work falls to each person on subsequent days. The workload of the same people across all projects at once is described in Resources in the organization.

The tab is available when the Resources module is turned on in the organization (see Resources module settings), the Resources functionality is turned on in the project (see Project functionalities) and the user has access to this module in the project (see User permissions).

Effort of tasks without owners

Effort is the number of hours (or days, if the organization counts in MD) that must be spent on a task.

  1. On the Schedule tab, in the List view, click the field in the Allocation column next to the task, or open the task panel and click the effort field.
  2. Enter a value (up to two decimal places) and press Enter. FlexiProject saves it on the task.

The effort unit, hours or MD, applies to the whole organization and is set in the system settings. Changing the unit is described in Resources module settings.

Important: A task without owners and departments keeps the effort as its own value, but it is not assigned to any person, so it does not count towards the workload of employees.

The effort of a summary task is the sum of the effort of its subtasks, so you cannot enter it directly.

Effort of tasks with owners

When a task has owners or departments, its effort is split equally between the departments and the owners who do not belong to any department. A department’s share is then split equally between the department members who are owners of the task. A department in which nobody is an owner of the task keeps its share at the department level.

Diagram: a task's allocation is split equally between departments and owners outside departments, a department's share equally between its members who own the task, and each person's share equally over the task's working days on which the person is available

A person’s share is spread equally over the working days of the task on which the person is available. Days off and days without availability, for example because of a vacation, are skipped (see Default user capacity). The effort can be spread over days only when the task has dates.

You can change the effort distribution manually in two ways.

Changing an owner’s total

  1. On the Resources tab, expand the person’s row and click the value in the Allocation column next to the task.
  2. Enter a new value and press Enter. FlexiProject spreads it again, equally over the working days of that person’s task.

Expanded person row on the Resources tab with the effort of their tasks

Changing the value for a range of days

  1. On the schedule list, click the field in the Allocation column of a task with owners, or the effort field in the task panel. The Allocation window opens.
  2. Click the cell of a day, week or month (depending on the scale) next to a person, enter a value and press Enter. The value is spread equally over the working days of that range.

Allocation window with the task workload split by departments and owners over consecutive days; the owner row with day values is highlighted in red

Important: Both changes also change the effort of the task, because it is the sum of the values of owners and departments. The effort of the other owners stays unchanged, and when you change a range of days, the other days of that person stay unchanged as well.

The values on the Resources tab can be edited by a person with the Admin level in the Resources module.

Effort recalculation when adding owners

What happens to the effort after an owner is added or removed depends on the Allocation calculation method setting in the Resources module settings:

  • Task duration priority (default) – the task effort is primary. After every change of owners, it is split again between all owners.
  • Owner duration priority – the owners’ effort is primary and does not change when further owners are added or removed. The first owner of a task gets the whole effort of the task, each subsequent owner has zero by default, and the task effort is the sum of the owners’ effort.

Important: The setting applies to the whole organization (see Resources module settings).

Allocation on the Resources tab

The Resources tab in the project shows the workload of team members on a timeline. The following settings are available above the table:

  • scale – day, week or month (the zoom slider on the right),
  • view – User, Department or Department > User (department views are available when the organization has departments),
  • unit – Hours (Man-day when the organization counts in MD), Percentages (workload against capacity) or Tasks (number of tasks),
  • workload – Current project or All projects, to see whether a person is overloaded with work in other projects.

Project Resources tab with the view, unit, workload range, export and scale options

The cell color shows whether the workload fits the person’s capacity: green means that the workload fits the capacity, and red means that it exceeds it. The color takes into account the workload from all projects, even when the cell shows a value from the current project only. Hover over a cell to see the details: the capacity and the workload from the current project and from other projects.

To export the view, click Export and choose a format: Document (.pdf), Image (.png) or Microsoft Excel (.xlsx).

Workload on the Gantt chart

The resource workload panel can be shown below the Gantt chart.

  1. On the Schedule tab, switch to the Gantt view, click Chart above the chart and turn on the Resource workloads switch. The panel appears below the chart.
  2. Choose whether the panel shows the workload from the project (Current project) or from all projects (All projects).

After you move a task on the chart, the panel recalculates the workload of employees.

Chart menu with the Resource workloads switch and the workload panel below the Gantt chart