Schedule attributes
Schedule attributes are custom columns of schedule items (tasks, summary tasks and milestones), available alongside the standard ones such as start date, duration, allocation or progress. They are used to categorize tasks and record additional information that the standard fields do not cover.
A system administrator defines the attributes in System settings. They are shared across the whole organization, and in a given project you choose which of them are used in the schedule.
Attribute types:
- Text – any text, for example a work order number or a short note on a task.
- Number – a numeric value with a fixed number of decimal places (from 0 to 6), for example the cost of a task. It can be summed up in summary tasks.
- Date – a date chosen from the calendar, for example an acceptance deadline.
- Single-choice list – one value from a prepared list of options, for example a task category. Each option has a name and a color. You can color the bars on the Gantt chart by the options (see Customizing the Gantt chart) and group the cards in Kanban by them (see Grouping cards).
- Link – an address (URL), for example a link to a document.
Defining schedule attributes
Attributes are created and changed in System settings, on the Schedule attributes tab. This is an organization-wide setting, available to the system administrator.
- In the main menu, choose System settings and go to the Schedule attributes tab.
- Click New attribute. The Add attribute window opens.
- In the Name field, enter the attribute name. Filling in this field is required.
- Optionally, enter a Description. The description is displayed as a tooltip next to the attribute name in the item panel.
- Choose the Type: Text, Number, Date, Single-choice list or Link.
- Single-choice list – add at least one option. Each option has a name and a color.
- Number – set the Decimal places (from 0 to 6) and, in the Value aggregation field, choose None or Sum.
- Optionally, turn on the Required field switch.
- Click Save. The attribute is added to the list of schedule attributes.

Important: The attribute type cannot be changed after the attribute is created.
Required field. A required attribute is added to all existing projects and project templates, and to every new project. In the attribute selection window of a project, its switch is permanently turned on. Optional attributes are turned on separately in each project.
Aggregation: Sum. For attributes of type Number with the Sum aggregation, you enter the value only on items without subitems. The value of a summary item is the sum of the values of its subitems and is recalculated automatically.
Attribute order. The order is set in System settings by dragging attributes in the list. It applies in the item details panel and in the attribute selection window in a project. The order of columns on the schedule list is set separately (see Customizing the schedule list view).
Changing and deleting an attribute
To change an attribute, click its name in the list on the Schedule attributes tab. The Edit attribute window opens, with the Delete and Save buttons. A new attribute name appears in saved reports immediately.
Changing the attribute settings affects values that have already been entered:
- deleting an option from a list removes the value of this attribute in the items that had it,
- reducing the number of decimal places rounds the saved values,
- changing the aggregation to None clears the aggregated values in summary tasks.
Warning: Deleting an attribute removes its values in all projects and templates, and removes the attribute from reports. The operation cannot be undone.
Important: Saving a change or deleting an attribute makes it impossible to undo earlier schedule changes in all projects (see Undoing schedule changes).
Schedule attributes in a project
Choosing attributes in a project
- Open the project, go to the Schedule tab and click Settings. A menu expands.
- Choose Schedule attributes. A window with the list of attributes defined in the organization opens. The item is visible when at least one attribute is defined in the organization.
- Turn on the switches next to the attributes that should be used in the project. Required attributes are always turned on.
- Click Save. The chosen attributes appear as fields in the item details panel, and they can be turned on as columns on the schedule list.

Important: Attribute columns on the schedule list are turned off by default. You turn them on with the Columns button (see Customizing the schedule list view).
Entering values
- On the schedule list – click the attribute cell in the item row, type or choose a value and confirm it by clicking outside the field or pressing Enter.
- In the item details panel – click the item name to open the panel, then type or choose a value in the attribute field and confirm it the same way.
For a Link attribute, you enter the value in the Add link window, in the URL field, and confirm it with the Save button.
You can also change attribute values for many items at once (see Bulk edit).
Schedule attributes in reports
- In the main menu, choose Reports.
- Open a report of the Schedule type or create a new one (see Reports). The report covers tasks and milestones.
- Click Columns. The Column settings window opens.
- Click Add column and choose a schedule attribute from the list.
- Click Save. The chosen attributes appear as columns in the report results.