Budget forecasts

A forecast is an amount expected on a given day: a planned cost or revenue. A budget item can have many forecasts spread over time. Their total is the item’s Forecast.

The By period view shows how forecasts are distributed across periods (see Budget views). Users with the Admin permission for the budget add, change and delete forecasts.

Adding a forecast

  1. On the Budget tab, click an item name. Its panel opens.
  2. On the Forecast tab, click Add forecast. A new row appears.
  3. Enter the amount and press Enter. The forecast is saved with today’s date. To change the date, use the date field.

Budget item panel with the Forecast tab and the list of forecasts; the Add forecast button is highlighted in red

A forecast can also be entered directly, without opening the panel:

  • in the list, in the Forecast column of an item that has one forecast or none,
  • in the By period view, in a period cell.

When the item is linked to the schedule, a new forecast gets the date that follows from the task and the set offset (see Linking forecasts to the schedule).

Important: Forecasts are added to a regular item. A summary item has no forecasts of its own, because it adds up the forecasts of its child items.

An amount can have at most two decimal places. To delete a forecast, click the cross at the end of the row.

Shifting forecasts in time

When the spending schedule moves, you can shift all the forecasts of an item at once.

  1. Open the item menu (right-click in the list, or the three-dot icon in the upper-right corner of the item panel) and choose Shift forecasts in time. The shift window opens. The option is visible when the item has forecasts.
  2. Choose the unit (Days or Months) and enter how far to shift the forecasts. A negative value moves them back.
  3. Click Shift. The forecast dates change and the amounts stay the same.

Shift forecasts in time window with the unit selection (Days or Months) and the value field; the window is highlighted in red

Important: The shift also covers forecasts linked to tasks. Their offset relative to the task is recalculated so that it matches the new date.

Removing past forecasts

Forecasts from past periods that were never realized inflate the budget. You can remove them with a single command.

  1. Choose the scope:
    • the whole budget: click Settings above the budget list,
    • one item together with its child items: open the menu of that item (three-dot icon next to the row).
  2. Choose Zero out past forecasts. The window lists the forecasts concerned and their total. The option is visible when the selected scope has past forecasts.
  3. Click Zero out. The past forecasts are removed.

Zero out past forecasts window over the budget List view; the description of the operation scope is highlighted in red

Important: Past forecasts are those dated before the first day of the current month, regardless of the scale of the By period view.

Actuals and the baseline stay the same. Zeroed forecasts are removed from the item rather than saved with an amount of 0.

An item’s forecasts can follow a task or milestone of the schedule. When the element’s date changes, the dates of the linked forecasts are recalculated.

Link to schedule element window with the expanded list of forecast offsets (No dependency, Task start, Task end); the Schedule field and the offset list are highlighted in red

Linking an item

  1. Open the item menu (three-dot icon next to the row in the list, or in the upper-right corner of the panel) and choose Assign to schedule. The Link to schedule element window opens.
  2. In the Schedule field, choose the element.
  3. In the Forecast offset relative to the schedule section, choose how the dates of new forecasts are determined: No dependency, Task start or Task end. For the last two, also choose the unit:
    • Days (Follow the exact date),
    • Months (Keep the same day of month).
  4. Click Save. The item is linked to the schedule element.

When the item is already linked, the menu option is called Edit schedule assignment. The link can also be changed in the Schedule field in the panel. Only a regular item can be linked, not a summary item.

Important: The setting in the window is the default for forecasts added later and does not change existing ones.

Linking a single forecast

When the item is linked to the schedule, the Forecast tab in the panel gets the Schedule dependency column. For each forecast, you can choose No dependency, Task start or Task end in it, and then enter the offset as a number with the Days or Months unit.

The date of a linked forecast is the task start or end date plus the offset. If you change the date of such a forecast manually, the offset changes and the link stays. Choosing No dependency detaches the forecast from the schedule and keeps its date.

Effects

The Delete button in the link window (after confirmation) detaches the item and all its forecasts from the schedule. Their dates stay as fixed dates.