Budget items
A budget item is a single cost or revenue in the project budget, such as “Licenses”, “Training” or “Client payment”. Items can be grouped into summary items, which add up the values of their child items.
Items are available on the project’s Budget tab (see Project budget). Access depends on the Budget project permission (see Project permissions):
- the View level lets the user browse items,
- the Admin level lets the user add, change and delete them.
Adding an item
- In the project, open the Budget tab and choose the List or By period view.
- Click New cost. To add revenue, click the arrow next to the button and choose New revenue. A new row with the name field appears in the list.
- Enter the name and press Enter. The item is added below the selected list row, or at the end of the list when nothing is selected.

After you save with Enter, another empty row of the same type appears below, so you can enter items one after another.
An item can also be added in a chosen place. The row menu (right-click or the three-dot icon next to the row) has the Add cost and Add revenue options with the Above, Below and Sub-item submenu. Further editing is done in the panel (see Item panel).

Structure and order of items
Items are arranged in a tree. An item that has sub-items is a summary item: it has no amounts, dates, forecasts or actuals of its own, and its values are the sum of its child items. A summary item can contain costs, revenue, or both.
- Adding a sub-item – the Sub-item option in the row menu (see Adding an item).
- Moving – dragging a row by the handle on the left changes its order or moves it under another item. An item cannot be moved into itself or into its own sub-item.
- Color – the Color option in the row menu colors the row.
Adding the first sub-item turns a regular item into a summary item. The result depends on how the sub-item is added:
- A sub-item added with the Sub-item option and of the same type as its parent takes over the parent’s amounts, forecasts, actuals, schedule link, attributes and color.
- In all other cases, the parent item loses its own amounts, forecasts, attributes and schedule link.
Warning: In the second case, actuals assigned to the parent item become unassigned, and actuals mapping rules that point to it are removed.
Cloning and changing the type
Cloning
Cloning creates a copy of an item, which speeds up entering similar costs or revenue.
- Open the item menu: right-click the row or click the three-dot icon next to the row, or use the menu in the item panel (three-dot icon in the upper-right corner of the panel).
- Choose Clone Cost (Clone revenue), or Clone in the panel. The copy appears below the original, with a suffix added to the name.
- The copy keeps the type, amounts, forecasts, schedule link, attributes, description, attachments and color.
- The copy does not take over actuals, the baseline, comments or change history.
- Cloning a summary item creates an empty summary item with no sub-items.
Changing the type
The Change to revenue and Change to cost options in the item menu change the item’s type.
Important: Actuals assigned to the item are detached in the process (they go to the Unassigned row), because the type of an actual must match the type of the item.
Item panel
The panel opens when you click an item name, or with the Show details option in the row menu. It contains:
- the name, which can be changed directly in the panel,
- the Actual, Forecast and Total amounts and, when a baseline that includes the budget has been approved, also Progress, Difference and Baseline (see Forecast, Actual, Baseline and difference),
- the Forecast and Actual tabs with the item’s entries over time, which can be narrowed with a date range (see Budget forecasts and Budget actuals); in a summary item they are read-only,
- the Schedule field with the linked schedule element (see Linking forecasts to the schedule),
- item attributes (see Budget item attributes),
- a description and attachments (a file, a link or an existing project file),
- the Comments (with mentions) and History tabs.

The panel menu (three-dot icon in the upper-right corner of the panel) has these options: Copy link, Add actual, Assign to schedule, Shift forecasts in time, Change to cost or Change to revenue, Clone, Zero out past forecasts and Delete. Shift forecasts in time and Zero out past forecasts are visible only when the item has forecasts to shift or past forecasts to zero out.
Editing in the list
- Name – the Rename option in the row menu, or a click on the name.
- Forecast – clicking the amount of an item that has one forecast or none changes that forecast or adds the first one (clearing the amount deletes it). With several forecasts, the amount is a sum and cannot be edited.
- Start date and End date – editable only in an item with a single entry (one forecast or one actual). In other items, they come from forecasts and actuals.
- Amount and Actual are sums and cannot be edited.
- Attributes – clicking a cell opens an editor that matches the attribute type.
Amounts are entered as positive numbers. The sign follows the item type.
Budget views
The Budget tab has three views, switched on the right side of the bar: List, By period and Actuals. The Actuals view is described in Budget actuals.

List
The list is a tree of items with columns. By default, it shows End date, Amount, Forecast and Actual. The Columns button adds and hides columns and sets their order. The available columns are Start date, Progress, Difference and Difference [%], item attributes and, after a baseline that includes the budget is approved, Baseline. The Total row includes the values of the whole budget, and the Unassigned row shows actuals that are not assigned to any item. The Export button saves the list to a file.
By period
The By period view shows item amounts split into periods. The scale switch has the Month, Quarter and Year values. The Rows button chooses which series are shown for each item: Forecast, Actual and, after a baseline that includes the budget is approved, Baseline and the difference in amount and in percent. Period amounts can be edited in the same way as a forecast in the list. The Export button saves the view to a file.
Filter
The Filter button (in the List and By period views) narrows items by name, type (costs, revenue), the range of start and end dates, and attribute values.
Important: Closing the filter bar removes the filter.
The browser remembers column, series, scale and filter settings for each project.
Importing items
Import loads many items at once from a project template or a file. The options are in the Settings menu above the budget, under Import budget items, available to users with the Admin permission for the budget.
From a template
- Choose From template. The Budget import wizard opens.
- Choose a project template and enter the start date. Item dates are recalculated relative to that date.
- Click Next, check the preview in the Budget preview step and confirm the import. The template items are added to the budget.
The list contains only templates assigned to the project’s workspaces (see Workspaces and template permissions).
From Microsoft Excel
- Choose From Microsoft Excel. The import wizard opens.
- Upload the file (supported formats: .xlsx and .csv, maximum size 10 MB). To download a template file, click Download template. The sample items in the template file must be deleted before the import.
- Click Next and assign the file columns to fields: Name, WBS, Description, Forecast, Actual, item attributes or Skip. For amount columns, enter the date format.
- Confirm the import. The items from the file are added to the budget.
File requirements:
- the name column is required,
- columns cannot repeat,
- forecast and actual amounts in one row must have the same sign.
The item type follows the sign of the amount:
- if the file has positive and negative amounts, positive ones become revenue and negative ones become costs,
- if there are only negative amounts, all items are costs,
- if there are only positive amounts, the system asks whether to import them as costs (Imports costs) or as revenue (Imports revenues).
Deleting an item
- Open the item menu in the budget list (right-click or the three-dot icon next to the row) or the menu in the item panel (three-dot icon in the upper-right corner of the panel).
- Choose Delete. The Delete budget item window opens.
- Confirm the deletion. The item disappears from the budget, and the values of the parent item and the project totals are recalculated.

Deleting an item also removes its child items, all its forecasts, its change history and the actuals mapping rules. Actuals assigned to the deleted items are not deleted; they go to the Unassigned row.
Warning: Deleting an item cannot be undone.
Budget item attributes
Budget items can be described with custom attributes, similar to projects. A system administrator defines item attributes: in the main menu, select System settings, open the Budget tab, then the Budget items tab, and use the New attribute button in the Budget attributes section.
Supported attribute types:
- short and long text,
- single-choice and multiple-selection list,
- number,
- date,
- link,
- function field (calculations on dates or numbers, for example the gross amount as the net amount multiplied by VAT).
Attributes are visible in the item panel and as columns of the budget list (the Columns button). Values can be edited in the list or in the panel. Summary items have no attributes (see Structure and order of items).
Actual attributes, separate fields that describe an actual, are defined in the same Budget tab, on the Actuals tab (see Budget actual attributes). Decimal places and Amount display are also set on the Budget items tab (see Currency and decimal places).