Creating a project
You create a new project in the Projects module. Click New project and choose one of the available options:
- Blank – a project without an initial schedule,
- From template – contains the schedule, budget, risks and products carried over from a previously prepared template,
- From Microsoft Excel – generates a schedule from an .xlsx or .csv file,
- From Microsoft Project – carries over a schedule from an .mpp file,
- With AI – builds a schedule automatically from the description you provide (available when AI is turned on in the FlexiProject instance).

A project can be created by a person who has permission to create projects in a workspace. If you have this permission in several workspaces, the Workspaces field appears during creation, where you choose the target workspaces. If you have the permission in one workspace only, the field does not appear and the project goes there automatically.
The project creation process ends with the Functionalities step, where you choose the modules (for example, Budget, Risks or Chat). The Schedule module is always turned on. You can change the selected modules later (see Project functionalities).

The person who creates the project automatically becomes its project manager, and the project gets the first status defined in the project status list. After the setup is finished, the project opens in the schedule view.
Adding a blank project
- Click New project and choose Blank from the list. The New project window opens.
- Enter the project name and, if needed, choose the workspace.
- In the Functionalities step, choose the project modules and confirm.
FlexiProject creates a blank project with no tasks and with a default working-day schedule of Monday to Friday. You build the schedule from scratch (see Adding schedule items).
Adding a project from a template
- Click New project and choose From template.
- Enter the project name and choose the workspaces. The Project template field shows the templates available for the selected workspaces (see Workspaces and template permissions).
- Choose a template from the Project template list.
- Select Start date or End date and enter the date. The schedule is recalculated forward or backward from that date.
- Choose the project Working days (the selected date must be a working day).
- In the Functionalities step, select the modules you want to use.
- In the Schedule view step, check the prepared schedule and confirm it.

The following items are carried over from the template to the new project:
- tasks and milestones with their dependencies (with dates recalculated from the selected date),
- effort assigned to owners and departments,
- the column layout of the schedule list,
- budget items with their forecasts and actuals mapping rules,
- risks, products and attached files.
If there are no templates available for the selected workspaces, the system displays the message: No project templates available. To prepare a template, see Project template.
Importing a project from Excel
- Click New project and choose From Microsoft Excel. The import wizard opens.
- Upload an .xlsx or .csv file (the maximum size is 10 MB). If you do not enter a project name, the file name is used.
- In the Data mapping step, assign a field to each column of the file: WBS, Name, Start, End, Duration, Progress, Description, Owner – email or Skip. Columns with standard headers are assigned automatically.
- For columns with dates, choose the Date format used in the file.
- Correct the cells marked in red in the list, choose the modules in the Functionalities step and finish the wizard.

Rules for reading the file:
- Only the first sheet is processed.
- The column with the task name is required.
- The WBS column defines the structure (for example, task 1.2 is placed under task 1).
- Progress is entered as a percentage (from 0 to 100).
- Task owners are matched by the email addresses of users registered in the organization (separate several addresses with a semicolon; unknown and incorrectly entered email addresses are skipped).
Important: An Excel import does not carry over dependencies between tasks. Add them in the schedule after the project is created. The working days of the project are set to every day of the week. If the team does not work at weekends, change the working days right after creating the project. After you change them, the task dates are recalculated and the operation cannot be undone.
Importing a project from MS Project
- Click New project and choose From Microsoft Project. The import wizard opens.
- Select an .mpp file. The project name is filled in automatically from the file.
- In the Data mapping step, choose how the dates are calculated:
- Recalculate dependencies – task dates are updated based on the relations and durations,
- Keep dates – the dates from the file stay unchanged, and lags are added to the dependencies.
- Review the change tables, choose the modules in the Functionalities step and finish the wizard.

The tables in the wizard show the changes required during the import:
- items with changed dates,
- milestones converted into tasks (only items with zero duration keep the milestone status),
- removed dependencies that caused conflicts.
If the file does not require any corrections, the wizard goes straight to the Functionalities step.
The following items are carried over from the .mpp file to the project:
- tasks and milestones with their hierarchical structure,
- dependencies between tasks, including lags,
- task progress,
- notes (saved as the task description),
- working days and days off from the calendar,
- resources from the file (assigned as task owners if their email address matches a user in the organization),
- baselines from the file, saved as approved project plans named Microsoft Project [0], Microsoft Project [1] and so on (see Project plan).
Adding a project with AI
- In the Projects module, click New project and choose With AI. The Describe your project window opens.
- Enter the project description: the goal, the main stages and the expected duration (the description must be 5 to 500 characters long).
- If you have permissions in several workspaces, choose the workspace.
- Click Generate. Generating the structure may take a moment, after which the finished project opens in the schedule list.
FlexiProject generates a name, a description, a start date and a schedule with tasks and their durations, arranged into a hierarchy of summary tasks and subtasks. The project is saved immediately and opens in the schedule list, where you can edit it freely.
Important: In a project generated by AI, every day of the week is a working day. If the team does not work at weekends, change the working days right after creating the project. After you change them, the task dates are recalculated and the operation cannot be undone.
Important: This option skips the Functionalities step. All modules are turned on automatically in the generated project.