Acceptance paths
An approval path is a template of a decision process that a project baseline (and with it a project charter) goes through before approval. It consists of consecutive stages, and each stage consists of people who make a decision or give an opinion.
Paths are available in the main menu, under Approvals, on the Approval paths tab (see Approvals). The list has the Name column and, when the organization uses workspaces, the Workspaces column. Click a name to open the path window.
The tab is visible to users with the approval path permission in a workspace (see Workspaces and approval paths). A path is chosen when a baseline or a charter is sent for approval (see Approving a baseline change).
Creating an approval path
- In the Approvals section, open the Approval paths tab. The list of paths appears.
- Click Add. The Approval path window opens.
- In the Name field, enter the path name. In the Workspaces field, choose the workspaces (the field is visible when the organization uses workspaces). Optionally, enter a Description. The description is shown when the path is chosen in the Approval window.
- Click Add stage and define the approvers (see Stages and approver roles). A new stage with a list of approvers appears.
- Click Add. The path is saved and appears in the list.

Saving a path requires:
- a name,
- at least one workspace,
- at least one stage,
- at least one person with the Decision action in every stage.
To change or delete a path, click its name in the list. The same window opens, where you can make changes or delete the path. Adding or removing a workspace requires permissions in that workspace (this does not apply to a system administrator).
Important: Deleting a path does not interrupt approvals that have already started. Changing or deleting a template does not affect paths that are already running in projects.
Workspaces and approval paths
Every path is assigned to one or more workspaces. The assignment decides:
- Where the path is available – in a project’s Approval window, the Approval path list contains only paths that share a workspace with the project. A path from another workspace cannot be used (such sending is rejected),
- Who manages the path – a user with the Approvals permission in a workspace can add, edit and delete that workspace’s paths and see the Approval paths tab. The list shows such a user only the paths of their workspaces.

The Approvals permission is granted in the workspace permissions of a user or a user group: the Configuration group, Approvals column.
A new path can be assigned only to workspaces where the user has this permission. When the user has it in only one workspace, the Workspaces field is not displayed.
To grant permissions for workspaces, see Users and permissions; for what workspaces are, see Workspaces.
Stages and approver roles
Stages
Stages are processed in order: stage 2 starts only after stage 1 has ended.
Add a stage with Add stage, and delete it with Delete in the stage menu (three-dot icon next to the stage). To change the order, drag a stage by its handle.
In the stage header, the sentence Approval requires decision of [all / any] Approvers defines how many decisions close the stage:
- all – the stage ends after decisions from all people with the Decision action,
- any of – the decision of the first one is enough.

Important: A stage also ends at once when any decision maker chooses Reject or Needs work. The whole approval then ends with that result, and further stages do not start.
Approvers
The Add approver button adds a row with a choice list. An approver can be:
- Project manager – the managers of the project in which the approval takes place (a dynamic value),
- a project role – the people assigned to the chosen role in the project (a dynamic value). A role can appear in a stage only once,
- Line Manager – the line manager of the person who sends the request for approval (a dynamic value). The line manager is set in the user profile (see Users and permissions),
- a specific user from the list of active users.
Important: Dynamic values are determined at the moment the baseline is sent for approval, from the data of that project.
If a person is in a stage twice (for example as project manager and as a member of a project role), one entry remains. It has the Decision action if either entry had it.
When a baseline is sent, the Approval window checks the path and marks errors:
- no project manager,
- a role with no people assigned, or not added to the project,
- no line manager,
- an inactive user,
- a license lower than Full.
Sending with an error is blocked.
Approver action
For each approver, the choice list has two values:
- Decision – a binding vote. The stage does not end without decisions (as set by all or any of),
- Opinion – an advisor. They can leave a comment and a choice, but do not close the stage.
The approver row menu (three-dot icon next to the approver) has these options:
- Information for the approver – a short message shown to the approver at decision time, marked with a comment icon,
- Delete.
For notifications to approvers and the course of the approval, see Project baseline.
Required approval path
A system administrator decides whether baselines and project charters can be approved without an approval path. The setting is in the main menu: System settings, Approvals tab, the Require approval path switch. The change is saved at once.

- Switch off (the default) – the Approval path list in the Approval window has the Empty option. Choosing it approves the baseline or charter at once, with no approvers.
- Switch on – there is no Empty option, and the send button is inactive until a path is chosen. The system also rejects sending without a path. Every baseline and every charter must go through a defined path.
Warning: Approval with no path cannot be undone and saves the baseline values, provided the Schedule and Budget switches are on (see Approving a baseline change).