2021.05

New budget interface

The new project budget interface has become more intuitive and resembles the project schedule in functionality. Adding elements works the same way as on the schedule; however, instead of tasks and milestones, there are expenses and revenues.

Users can add new elements using a button in the top-left corner or by right-clicking on an existing element to access the following functions:

In comparison to the previous version, users can now create a hierarchical tree structure within the project budget. This enables planning an initial estimated budget early on and expanding it with more detailed items as the project progresses. The budget table is fully editable, allowing users to change dates, amounts, and cost locations without accessing detailed views.

Clicking on an element’s name displays its details on the right side of the screen. From there, users can manage all properties, including dates, descriptions, amounts, and attachments. In the new FlexiProject version, users can also add comments to budget elements and view their complete history.

A significant change from the previous system version is marking budget elements as completed. This works similarly to the project schedule. To mark a budget item as completed, users click the icon before the element’s name. For forecasted elements with past dates that remain unmarked as completed, the date will appear in red.

Export and filtering

The new project budget in FlexiProject includes more advanced table-related functionalities. Users can filter selected elements by name, type (expense, revenue), status (forecast, completed), and dates. Additionally, the table can be exported to Excel, and each user can individually manage column visibility in the Budget tab.

Revenues in the budget

In addition to expenses, users can now define revenues for each project. Budget elements are visually differentiated with icons and amounts. Expenses are marked with a circle containing a dollar symbol and have negative values, while revenues are shown as dollar bags with positive values highlighted in green.

Linking expense and revenue dates with schedule dates

As before, budget elements can be linked to project schedule elements. Now, users can decide whether expense dates depend on schedule dates. If such a link is created, shifting the schedule dates will also shift the expense dates. Budget item dates can also depend on the start and end dates of specific tasks and milestones, with the option to define a margin in days. Dates derived from the schedule will display an additional icon in the budget and cannot be manually changed.

 

Project plan change window

The project plan change window has been updated. New functionalities allow users to specify which elements—schedule, budget, or project card—should have their plans archived. If the schedule or budget is disabled, their respective tabs will not appear on the project card.

Project portfolios – project list

The project portfolio view has undergone changes in the new FlexiProject version. The previous tab displayed upon entering a project portfolio is now located under the “Scoring” tab. The main tab for portfolios is now a list of all associated projects. From this view, users can add or remove projects from the portfolio. By default, archived projects are hidden, but users can display them using the “Show Archived” filter. Users can also create new overviews for projects within the portfolio from this level.

Project portfolios – consolidated Gantt view

The project portfolio view now includes a consolidated schedule for all projects within the portfolio. The tab displays a Gantt chart with milestones from each project, their statuses, and overall project progress. Users can also display baseline plans and project managers on the chart. Options for managing element visibility and time scale are available. The consolidated Gantt chart can be exported to PDF or an image file.

Schedule – list of recent changes

Users can enable a “Last Change” column in the project schedule. This column displays the time elapsed since the last modification of a schedule element. The column can be shown or hidden and reordered using the “Columns” button.

New attachment interface

All attachments added to tasks, milestones, budgets, risks, products, or plan changes are now displayed using icons. The method of adding attachments remains the same, but the option to delete them is visible when hovering over a specific attachment.