Logo
  • Features
    Project Management
    Ikona dla Project scheduleProject schedule
    Ikona dla Gantt ChartGantt Chart
    Ikona dla Kanban boardKanban board
    Ikona dla Project charterProject charter
    Ikona dla Project planProject plan
    Ikona dla BudgetBudget
    Ikona dla Project risksProject risks
    Ikona dla ProductsProducts
    Ikona dla CommunicationCommunication
    Strategic project management
    Ikona dla Project PortfoliosProject Portfolios
    Ikona dla Project templatesProject templates
    Ikona dla ReportsReports
    Ikona dla Project reviewsProject reviews
    Ikona dla StrategyStrategy
    Ikona dla Scoring modelScoring model
    Ikona dla Acceptance pathsAcceptance paths
    Ikona dla Knowledge baseKnowledge base
    Effective time management
    Ikona dla Work time registrationWork time registration
    Ikona dla ResourcesResources
    Ikona dla Operational workOperational work
  • Solutions
    For teams
    Ikona dla Project Management OfficeProject Management Office
    Ikona dla Management boardManagement board
    Ikona dla Finance & ControllingFinance & Controlling
    Industry
    Ikona dla CommercialCommercial
    Ikona dla PharmaceuticalPharmaceutical
    Ikona dla ManufacturingManufacturing
    Ikona dla ITIT
    Ikona dla Solar farmsSolar farms
    Use cases
    Ikona dla Integrated project managementIntegrated project management
    Ikona dla Strategic project managementStrategic project management
    Ikona dla Innovation and R&D projectsInnovation and R&D projects
    Ikona dla Recurrent projectsRecurrent projects
    Ikona dla Integration with JiraIntegration with Jira
    Ikona dla Quick WinsQuick Wins
  • Why FlexiProject?
    Ikona dla Configure your systemConfigure your system

    Reflect your own processes in FlexiProject

    Ikona dla Key features of FlexiProjectKey features of FlexiProject

    Uncover the unique qualities of FlexiProject

    Ikona dla Customers & Case studyCustomers & Case study

    Explore our customers stories

    Ikona dla FlexiProject featuresFlexiProject features

    Discover all the features of FlexiProject

    Ikona dla IntegrationsIntegrations

    Connect your tools for better efficiency

  • Resources
    Ikona dla Project management blogProject management blog

    Project management tips & trends

    Ikona dla User guideUser guide

    Explore FlexiProject in details

    Ikona dla Release historyRelease history

    FlexiProject's history of changes

    Ikona dla NewsletterNewsletter

    Stay up to date!

  • Pricing
  • Contact
    Ikona dla Contact salesContact sales

    Learn more about product, plans or pricing

    Ikona dla Contact supportContact support

    Get help with technical issues

    Ikona dla Become a PartnerBecome a Partner

    Join the FlexiProject Partner Program!

  • Log in
  • Get started
Language en
  • English
  • Polski
  • Čeština
  • Deutsch
  • Español
  • Français
  • Magyar
  • Italiano
  • Portuguese
  • Română
  • Українська
Log in
Get started
Table of contents

Project budget

Earned Value Method (EVM) explained – How to accurately measure project progress and performance

Measuring progress and controlling costs are two crucial aspects of project management. The Earned Value Method (Earned Value Management – EVM) enables you to combine scope, schedule, and budget within one cohesive methodology. Let’s explore how EVM implementation works and its practical application in modern project management tools.

Cost performance chart illustrating the Schedule Performance Index (SPI) in project management

In this article, you will learn:

  • What Earned Value Method (EVM) is and its key metrics (PV, EV, AC)
  • How to interpret CPI and SPI for cost and schedule performance
  • When and where EVM is most effective
  • How EVM works with Agile and hybrid projects
  • Benefits of EVM like early problem detection and better decision-making
  • Basic steps to implement EVM in your organization
  • How FlexiProject helps manage EVM easily and in real time

What is the Earned Value Method (EVM)?

Earned Value Management was born in the 1960s in the U.S. Department of Defense as a response to escalating costs and delays in large government projects. The fundamental premise of EVM project management is integrating three key project dimensions: work scope, schedule, and costs within one objective measurement system.

The method proved itself during NASA space programs and defense projects, where traditional control approaches proved insufficient. Today, EVM finds application in many areas, including construction, IT, pharmaceuticals, and other industries where precise project cost tracking and schedule monitoring are particularly important. The earned value method has become almost standard for high-value projects, though its principles can be successfully adapted to smaller undertakings as well.

The beauty of earned value analysis lies in its ability to provide objective, quantifiable insights into project health. Unlike traditional methods that might look at budget and schedule separately, EVM creates a unified view that reveals the true relationship between planned work, completed work, and actual expenditure.

Try FlexiProject for free!

Enjoy full access to FlexiProject for 30 days – no cost, no charge

Get started

The core metrics of EVM: PV, EV, and AC

The effectiveness of earned value analysis relies on three fundamental parameters that together create a complete picture of project status.

  • Planned Value (PV) represents the budget assigned to scheduled work at a specific point in time. It’s calculated using the formula: PV = (Planned % completion) × Budget at Completion (BAC). Planned value serves as the baseline against which project progress is measured. For example, if a project has a total budget of $100,000 and should be half-completed according to schedule, PV equals $50,000.
  • Earned Value (EV) is the budgeted cost of work actually performed. The formula EV = (Actual % completion) × BAC allows you to visualize physical work progress converted to financial value, providing a clear measurement. If in our example 30% of work is completed, EV equals $30,000 regardless of how much was actually spent on those tasks.
  • Actual Cost (AC) represents the costs actually incurred. This is the simplest parameter to measure, drawn directly from accounting systems. Continuing our example: if $45,000 was spent to complete 30% of the work, then AC = $45,000.

How to calculate EV PV AC in practice? The key is creating a detailed Work Breakdown Structure (WBS) and assigning each work package a specific budget and progress measurement criteria. Earned value can be measured using various methods, such as completed milestones (0/100% method). Most importantly, you’ll need appropriate software that we’ll discuss more extensively in the following sections.

Understanding these EV PV AC explained concepts forms the foundation for meaningful project performance analysis. Without accurate measurement of these three values, any attempt at earned value analysis becomes meaningless.

How to read EVM metrics: CPI, SPI, CV, and SV

The true value of the earned value method lies in its ability to forecast future results based on current project performance indicators.

  • Cost Performance Index (CPI) is calculated using the formula CPI = EV / AC. This indicator is the most important parameter in project cost control, as it shows what value you receive for every dollar spent. CPI = 1.0 means execution according to budget, CPI > 1.0 indicates execution under budget (favorable for the organization), and CPI < 1.0 indicates budget overrun.

In our earlier example, CPI = $30,000 / $45,000 = 0.67, meaning for every dollar spent, you receive only 67 cents of value. This is a warning signal requiring immediate intervention.

  • Schedule Performance Index (SPI) uses the formula SPI = EV / PV. This schedule performance index measures schedule execution efficiency. SPI = $30,000 / $50,000 = 0.60 shows the project is progressing at only 60% of the planned pace. There’s clearly significant room for improvement.
  • Cost and schedule variances provide information in monetary units. Cost Variance (CV = EV – AC) equals -$15,000, indicating budget overrun. Schedule Variance (SV = EV – PV) equals -$20,000, indicating schedule delays. Single measurements can be misleading, especially in early project phases.

These project performance indicators work together to paint a comprehensive picture of project health. Smart project managers don’t rely on just one metric but analyze trends across all indicators to make informed decisions.

See more

Burndown chart explained: what it is, how it works and why it’s essential for agile teams

Go to article

What values of CPI and SPI are red flags?

An effective early warning system based on earned value analysis relies on establishing alarm thresholds tailored to your organization’s and project’s specifics.

From an organizational perspective, critical warning levels play a key role. CPI below 0.8 indicates significant cost overruns, requiring rapid corrective action. CPI values between 0.8-0.9 signal cost problems requiring attention. Similarly, SPI below 0.8 means serious delays, while the 0.8-0.9 range requires monitoring.

Remember that monitoring trends proves more important than interpreting only individual values. A stable CPI at 0.85 might be acceptable, while a declining trend from 0.95 to 0.85 over several reporting periods requires analyzing the causes.

Importantly, after completing 15-20% of the project, EVM indicators provide reliable forecasts of final results. Well-configured alerts allow for corrections when the project is still in a phase that enables effective corrective actions. An important indicator here is Estimate at Completion (EAC), the forecast of the project’s final cost. It’s calculated as EAC = BAC / CPI. In our example, EAC = $100,000 / 0.67 = $149,254, indicating a projected budget overrun of nearly $50,000. Such a forecast should prompt those responsible to take corrective action as quickly as possible.

Understanding how to use EVM warning signals separates reactive project management from proactive leadership. Teams that establish clear thresholds and respond quickly to variance trends consistently deliver better project outcomes.

Projects with high cost sensitivity or time pressure

The earned value method is highly effective, but it’s not a universal solution for all project types. Its effectiveness depends on the project’s characteristics and the organization’s maturity in project control.

EVM works best in large and complex projects, typically those with high value and execution time exceeding 18 months. It finds its natural home in defense, aviation, and aerospace sectors. IT projects with fixed scope can also benefit from EVM implementation. However, traditional EVM faces challenges in agile projects where flexibility and scope modification are essential elements.

Research and creative projects present certain challenges. Difficulty in defining measurable work packages and unpredictability of results limit this method’s effectiveness. For budget forecasting in projects, EVM requires well-defined deliverables and clear success criteria.

For small projects with short duration, simplified EVM versions or less complex control tools may be more appropriate. The key is matching the control methodology to project complexity and organizational needs.

Projects operating under extreme time pressure benefit significantly from EVM’s early warning capabilities. When delays can result in penalty clauses or loss of market opportunities, the investment in comprehensive earned value analysis pays for itself many times over.

EVM and Agile – is it compatible?

One key factor determining whether EVM will work in a specific case is the project scope.

  • Fixed-scope projects provide ideal ground for classic EVM. Well-defined requirements, detailed work breakdown structure, and stable baseline enable precise deviation measurement and forecasting. Traditional Gantt chart in project planning works seamlessly with EVM in these environments.
  • Agile and flexible projects require certain adaptations. Traditional EVM relies on a fixed baseline, while agile projects feature iterative requirement establishment and modification processes. The solution may be AgileEVM: in this approach, story points play a larger role, enabling earned value calculation in agile environments.
  • Hybrid approaches are gaining popularity across many industries. They successfully combine traditional project management elements with agile methodologies. Workflow automation can support such environments, enabling flexible scope management while maintaining cost control.

Remember that change management in flexible projects requires special attention. Frequent baseline modifications can undermine EVM indicator reliability. The key is establishing clear rules for updating baseline PV values while maintaining comparison capability with original assumptions.

Modern organizations increasingly recognize that rigid adherence to either traditional or agile approaches limits their effectiveness. The most successful teams adapt their control methods to project needs rather than forcing projects to fit predetermined methodologies.

Applying EVM in FlexiProject – a practical example

Of course, today’s standard involves leveraging software support for collecting, analyzing, and organizing key data. Project management system FlexiProject enables creating detailed budget structures linked to task schedules. An important element is real-time process monitoring, which allows tracking work progress in the context of planned timelines and costs.

Practical implementation relies on project templates with properly configured work packages. Each package should have an assigned budget (forming the basis for PV) and clearly defined progress measurement criteria (enabling EV calculation). Actual costs (AC) are automatically registered in the system when entering costs and expenses. This enables EVM reporting and visual representation of the most important parameters.

Another advantage is integration with other systems and tools, enabling information flow automation. This allows you to seamlessly create a comprehensive control system tailored to your organization’s needs.

FlexiProject’s approach to real-time project reporting transforms how teams understand project health. Instead of waiting for monthly reports, project managers receive continuous updates on EVM indicators, enabling immediate response to developing issues.

The platform’s strength lies in making complex EVM calculations accessible to project teams without requiring extensive training in financial analysis. The system handles the mathematical complexity while presenting results in intuitive dashboards that drive actionable insights.

Try FlexiProject for free!

Enjoy full access to FlexiProject for 30 days – no cost, no charge

Get started

Why use EVM? Benefits for your organization

The Earned Value Method can bring organizations very concrete benefits. Let’s mention several of them:

  • Early problem detection is EVM’s most important advantage. The warning system based on CPI and SPI indicators identifies problems well in advance compared to traditional methods. It enables corrective action implementation when the project is still in a phase allowing effective intervention.
  • Objective decision support eliminates subjectivity in project progress assessment. Those responsible receive numerical data enabling informed decisions about resource allocation, scope changes, or schedule modifications. Reliable final cost forecasts (EAC) enable financial planning and expectation management for managing project stakeholders.
  • Coopers & Lybrand research showed that EVM implementation costs represent only 0.9% of contract value, while benefits can reach 25% savings compared to baseline budget with proper system implementation. Projects using EVM demonstrate higher predictability in timelines and budgets.
  • Improved stakeholder communication results from reporting transparency based on specific indicators. Regular EVM reports build trust between the project team and management while ensuring thorough understanding of project status.

The cumulative effect of these benefits extends far beyond individual projects. Organizations implementing EVM consistently report improved portfolio performance, better resource utilization, and enhanced client satisfaction due to more predictable project delivery.

How to get started with Earned Value Management?

Implementing the earned value method in an organization should be divided into several stages that help avoid the most common mistakes. An example process might look as follows:

  • Preparation phase involves analyzing the gap between current processes and EVM requirements. This assessment helps identify necessary changes in data collection, reporting procedures, and organizational culture.
  • Pilot project selection should consider medium complexity, clearly defined scope, and the ability to dedicate additional resources to system testing. New projects work best as they don’t require reconstructing historical data.
  • Information system integration forms the foundation of effective earned value analysis. Organizations need to connect ERP systems, scheduling, and project control into a cohesive reporting platform. Without technological components, EVM implementation becomes fundamentally unprofitable.
  • Training program should cover all organizational levels. Appropriate personnel should understand not only technical calculation aspects but also principles of indicator interpretation and decision-making based on them.

Starting with a limited scope allows organizations to build competency gradually while demonstrating value to skeptical stakeholders. Success with initial projects creates momentum for broader EVM adoption across the organization.

EVM + FlexiProject - monitoring, reporting, and control in one tool

To achieve the full benefits that earned value analysis provides, you need a comprehensive project management platform like FlexiProject. EVM software can be truly versatile: monitoring, reporting, schedule control, and project budget management are available in one tool. The system allows organizations of any size to implement EVM without extensive training or complicated configuration procedures. FlexiProject’s comprehensive approach includes automatic EVM indicator calculations, real-time data dashboards, and integration capabilities with existing tools.

You’ll be able to transform raw project data into practical insights through advanced reporting mechanisms. The system offers automated project reviews that streamline communication between management, PMO, and project managers. You can therefore monitor project progress instantly. Indicators that are calculated automatically will allow you to quickly find the most important information.

At the same time, you receive all the tools necessary for project planning and execution: from project cards and automated reviews to risk management and knowledge bases. This integrated approach eliminates the need to use multiple tools and ensures consistency across the entire portfolio, regardless of which project control method you use.

AUTHOR

Dominik Wrzosek

General Manager at FlexiProject

See more

How to Calculate Cost-Effectiveness in Projects and Improve Budget Efficiency

How to Calculate Cost-Effectiveness in Projects and Improve Budget Efficiency

Go to article
How do you create and control a project budget at the implementation stage?

How do you create and control a project budget at the implementation stage?

Go to article
How do you develop a project budget?

How do you develop a project budget?

Go to article
Features
  • Project schedule
  • Gantt Chart
  • Project charter
  • Project plan
  • Budget
  • Project risks
Features
  • Project Portfolios
  • Project templates
  • Reports
  • Project reviews
  • Strategy
  • Scoring model
Resources
  • Project management blog
  • Key features of FlexiProject
  • Customers & Case study
  • Newsletter
Contact
  • Contact support
  • Contact sales
Logo Footer
Copyright © 2025 flexi-project.com
·
Privacy policy
FlexiProject
Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
Manage options Manage services Manage {vendor_count} vendors Read more about these purposes
View preferences
{title} {title} {title}