Logo
  • Features
    Project Management
    Ikona dla Project scheduleProject schedule
    Ikona dla Gantt ChartGantt Chart
    Ikona dla Kanban boardKanban board
    Ikona dla Project charterProject charter
    Ikona dla Project planProject plan
    Ikona dla BudgetBudget
    Ikona dla Project risksProject risks
    Ikona dla ProductsProducts
    Ikona dla CommunicationCommunication
    Strategic project management
    Ikona dla Project PortfoliosProject Portfolios
    Ikona dla Project templatesProject templates
    Ikona dla ReportsReports
    Ikona dla Project reviewsProject reviews
    Ikona dla StrategyStrategy
    Ikona dla Scoring modelScoring model
    Ikona dla Acceptance pathsAcceptance paths
    Ikona dla Knowledge baseKnowledge base
    Effective time management
    Ikona dla Work time registrationWork time registration
    Ikona dla ResourcesResources
    Ikona dla Operational workOperational work
  • Solutions
    For teams
    Ikona dla Project Management OfficeProject Management Office
    Ikona dla Management boardManagement board
    Ikona dla Finance & ControllingFinance & Controlling
    Industry
    Ikona dla CommercialCommercial
    Ikona dla PharmaceuticalPharmaceutical
    Ikona dla ManufacturingManufacturing
    Ikona dla ITIT
    Ikona dla Solar farmsSolar farms
    Use cases
    Ikona dla Integrated project managementIntegrated project management
    Ikona dla Strategic project managementStrategic project management
    Ikona dla Innovation and R&D projectsInnovation and R&D projects
    Ikona dla Recurrent projectsRecurrent projects
    Ikona dla Integration with JiraIntegration with Jira
    Ikona dla Quick WinsQuick Wins
  • Why FlexiProject?
    Ikona dla Configure your systemConfigure your system

    Reflect your own processes in FlexiProject

    Ikona dla Key features of FlexiProjectKey features of FlexiProject

    Uncover the unique qualities of FlexiProject

    Ikona dla Customers & Case studyCustomers & Case study

    Explore our customers stories

    Ikona dla FlexiProject featuresFlexiProject features

    Discover all the features of FlexiProject

    Ikona dla IntegrationsIntegrations

    Connect your tools for better efficiency

  • Resources
    Ikona dla Project management blogProject management blog

    Project management tips & trends

    Ikona dla User guideUser guide

    Explore FlexiProject in details

    Ikona dla Release historyRelease history

    FlexiProject's history of changes

    Ikona dla NewsletterNewsletter

    Stay up to date!

  • Pricing
  • Contact
    Ikona dla Contact salesContact sales

    Learn more about product, plans or pricing

    Ikona dla Contact supportContact support

    Get help with technical issues

    Ikona dla Become a PartnerBecome a Partner

    Join the FlexiProject Partner Program!

  • Log in
  • Get started
Language en
  • English
  • Polski
  • Čeština
  • Deutsch
  • Español
  • Français
  • Magyar
  • Italiano
  • Portuguese
  • Română
  • Українська
Log in
Get started
Table of contents

Project plan

Critical path – what it is and how to manage it?

The critical path is a key component of project management that significantly influences a project’s success or failure. Understanding how the critical path works and effectively managing it are essential skills for every project manager. In this article, we’ll explore the critical path, how to identify it, and how to manage it effectively.

Critical Path in FlexiProject

What is the critical path?

The critical path is the longest sequence of tasks that must be completed to finish a project on time. Each task on this path is referred to as a critical task because any delay in completing these tasks will directly impact the project timeline. In project management, the Critical Path Method (CPM) is a tool that helps identify these key tasks and analyze their impact on the project schedule.

The critical path defines the minimum time required to complete a project and highlights tasks that demand special attention. In practice, all resources and risk management efforts should be focused on critical path since they directly affect the project’s timely delivery. Thus, the Critical Path Method is invaluable for planning and monitoring project schedules.

Understanding the critical path is crucial for successful project management, especially in complex initiatives requiring intricate and interconnected task dependencies. The critical path may change during the project, making regular monitoring essential to prevent unexpected delays.

Identifying the critical path

Identifying the critical path in a project involves several key steps to determine the tasks crucial for on-time project delivery accurately. Here’s a detailed breakdown:

  1. Define the List of Tasks:
    Begin by creating a comprehensive list of tasks required to complete the project. It’s essential to include every element of work. Using a Work Breakdown Structure (WBS) can help organize and prioritize tasks effectively.
  2. Estimate Task Durations:
    Estimate the duration of each task. Accurate estimates are vital since they directly impact the project schedule. Use experience, expertise, and data from similar projects to make reliable calculations.
  3. Identify Task Dependencies:
    Determine how each task is connected to others. Some tasks can only start after others are finished. In FlexiProject, dependencies can be defined using four types of relations: finish-to-start (FS), start-to-start (SS), finish-to-finish (FF), and start-to-finish (SF). These relationships help map out how tasks interact and influence one another.
  4. Create a Network Diagram:
    Create a network diagram based on the tasks and dependencies. This visual representation outlines the sequence of tasks and their connections, making it easier to understand the project structure and identify the critical path.
  5. Determine the Critical Path:
    Finally, identify the critical path, which is the longest sequence of tasks necessary to complete the project within the set timeline. While it’s possible to calculate the critical path manually, FlexiProject simplifies the process by automatically identifying it based on the project schedule and task dependencies. The critical path reveals which tasks are vital and require close attention to avoid project delays.

How to manage the critical path

Managing the critical path requires constant vigilance and regular monitoring of the progress of critical tasks. The Critical Path Method assumes that delays in critical tasks will directly affect the project timeline, making proactive management essential.

  1. Monitor Progress Regularly:
    Continuously analyze the schedule and compare actual progress to the planned timeline. If any delays are identified, take corrective action immediately, such as allocating additional resources to critical tasks or reorganizing the schedule.
  2. Manage Risks Effectively:
    Critical tasks are particularly susceptible to delays. Project managers should implement risk management strategies, such as identifying potential risks and developing contingency plans. The project team must also understand the importance of critical tasks and their impact on the overall project.
  3. Be Flexible to Changes:
    Unexpected circumstances during project execution may alter task schedules. In such cases, it’s crucial to assess how these changes affect the critical path and take the necessary steps to avoid delays.
  4. Ensure Effective Communication:
    Clear communication within the project team is key to managing the critical path. Regular meetings, progress reports, and open information sharing help maintain control over critical tasks and minimize risks of delays.

Critical path in FlexiProject

One of FlexiProject’s standout features is its ability to automatically identify the critical path based on the project schedule and task dependencies. The system analyzes all project tasks, determines dependencies, and pinpoints those that are critical to the project’s on-time delivery. This gives project managers full control over the schedule and allows them to respond quickly to potential risks.

FlexiProject also offers advanced tools for monitoring progress on critical tasks. The system enables real-time tracking, deviation analysis, and identification of potential delays in necessary tasks. These features make managing the critical path more efficient and significantly reduce the risk of project delays.

Moreover, FlexiProject facilitates seamless communication within the project team. It enables easy information sharing about the critical path and task progress, essential for successful project management. With FlexiProject, teams gain full visibility into the key aspects of the schedule and can collaborate more effectively to achieve project goals.

AUTHOR

Dominik Wrzosek

General Manager at FlexiProject

See more

The most flexible Gantt Chart software for project management

The most flexible Gantt Chart software for project management

Go to article
Establishing priorities in project management

Establishing priorities in project management

Go to article
What is a Work Breakdown Structure (WBS)?

What is a Work Breakdown Structure (WBS)?

Go to article
Project Life Cycle: Phases and key information you need to know!

Project Life Cycle: Phases and key information you need to know!

Go to article
Managing change in the project plan. How to prepare for unpredictable changes?

Managing change in the project plan. How to prepare for unpredictable changes?

Go to article
Features
  • Project schedule
  • Gantt Chart
  • Project charter
  • Project plan
  • Budget
  • Project risks
Features
  • Project Portfolios
  • Project templates
  • Reports
  • Project reviews
  • Strategy
  • Scoring model
Resources
  • Project management blog
  • Key features of FlexiProject
  • Customers & Case study
  • Newsletter
Contact
  • Contact support
  • Contact sales
Logo Footer
Copyright © 2025 flexi-project.com
·
Privacy policy
FlexiProject
Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
Manage options Manage services Manage {vendor_count} vendors Read more about these purposes
View preferences
{title} {title} {title}