Software compare

Trello alternative for project scheduling

Many teams start planning projects in Trello because a board takes minutes to set up and everyone sees what needs doing. The trouble starts on a project with a fixed end date, where one task can only begin once another one finishes. A Trello alternative for project scheduling is a system that recalculates dates from the dependencies between tasks. In Trello, you recreate task order with checklists and automation rules. In FlexiProject, you link tasks with dependencies on the Gantt chart and see the critical path and the variance against the baseline in the same schedule.

Key takeaways:

  • Trello — a tool for working on boards with task cards. The Timeline view, available in the Premium and Enterprise plans, shows card dates, but Trello has no built-in dependencies, so moving one card leaves the others in place.
  • What to look for in a Trello alternative for project scheduling — a schedule where dates follow from task dependencies and the effect of a delay on the end date shows right away, without checklist and automation workarounds.
  • FlexiProject: dates recalculated from dependencies — it supports four dependency types, fixed lag and a working-day calendar, recalculates linked tasks when a date changes and shows the critical path on the Gantt chart.
  • FlexiProject: baseline and Kanban board — you measure variance against an approved baseline, while the team keeps moving cards on a Kanban board that shows the same tasks as the Gantt chart.
  • How to test FlexiProject — during the 30-day free trial, import a schedule from an .xlsx or .csv file, link tasks with dependencies on the Gantt chart and turn on the critical path in the Chart menu.

Trello’s Timeline view shows card dates without dependencies between them

Trello organizes work in lists and cards, and the Timeline view lays dated cards out on a horizontal line. You see when each task starts and ends, and you can drag a card to a new date. That view shows what happens in a given week, but it does not show what happens to the end date when one task slips. For that you need a schedule in which dates follow from the order of work.

The Timeline view is available on Premium and Enterprise

According to Trello’s documentation, the Timeline view works only in Workspaces on Premium or Enterprise, and Trello has no plans to bring it to free Workspaces. It runs in the browser and desktop app, but not on mobile. You group cards by list, member or label, and undated cards sit in a separate unscheduled section. When you move one card, the others stay where they are, even if in reality they depend on it.

Try FlexiProject!

Stay on schedule! Test the Gantt chart in FlexiProject with 30 days free access.

FlexiProject

In Trello, you build dependencies from checklists and automation rules

Trello has no built-in task dependency management, as the vendor’s documentation confirms. The recommended setup stores each task as a card and its prerequisites as checklist items. You link each item to the card it depends on and add a link back on that card. Automation rules then react when a card moves or a checklist is completed.

An automation rule shifts sub-task dates by the same number of days

Rules can handle several steps. When a card reaches the “Completed” list, a rule ticks the matching item on dependent cards and adds a dated comment. When all prerequisites are met, the card gets a “Ready” label. According to the documentation, a separate rule moves the due dates of sub-task cards by the same amount as the parent card.

A rule cannot reproduce dependency types, a working-day calendar or a critical path

The rule shifts dates by a fixed amount and does not take into account whether a task should start after the previous one finishes or alongside it, and Trello keeps no project calendar with days off. Trello does not calculate a project’s critical path, so you cannot see which delay will push back the end date. Each rule works only on the board where it was set up.

Power-Ups add a Gantt chart through third-party apps

If your team wants to stay in Trello, you can add a Gantt Power-Up such as Le Gantt or Planyway. These add-ons place cards on a timeline. Your schedule then depends on another company’s add-on, which you choose, configure and enable on each board separately. Baselines, change approval and a view across many projects are not part of Trello itself.

Recalculating dependencies between tasks as a Trello alternative for project scheduling

In FlexiProject you build the schedule from phases, tasks and milestones, then link them with dependencies directly on the Gantt chart: you drag a dot from one task bar to another or choose “Add dependency” in the task menu. When you change a task’s date, FlexiProject recalculates the dependencies and moves the linked tasks. You see straight away how one delay affects the end date, and in the conversation with the sponsor you give a specific date.

Four dependency types and a fixed lag

A dependency defines the order of two tasks: finish-to-start, start-to-start, finish-to-finish or start-to-finish. These four types of task dependencies cover cases a Trello checklist cannot distinguish, such as testing that begins together with deployment. With a fixed lag you set a gap in working days between tasks, and it stays the same after you move the predecessor. That is how you plan time for document sign-off or a review period. Without a fixed lag a dependency is flexible: you can freely move the predecessor, and the successor stays where it is until, for a finish-to-start relation, the end of the predecessor passes the start of the successor, at which point the start of the successor moves to the end of the predecessor.

Edit dependency window in FlexiProject with the dependency type End - Start and the Fixed lag option
Edit dependency window in FlexiProject with the dependency type End – Start and the Fixed lag option

Working days and days off for each project

In the project settings you choose the working days of the week and add the project’s days off. After you save, FlexiProject recalculates the dates of all tasks and milestones, and a date that falls on a day off moves to the nearest working day. Each project has its own calendar, so a five-working-day task does not end on a public holiday you entered.

The critical path shows the tasks that drive the end date

You turn on the critical path with a switch in the “Chart” menu of the Gantt view. The chart then highlights the tasks and dependencies that determine the project’s end date. The project manager knows where to focus attention and people, and the sponsor understands why one late task is a problem and another is not. The path follows from the dependencies you entered.

Dependencies between tasks from different projects

You can create a dependency between tasks in two different projects, provided you have permission to the other project. That helps when a system rollout can only start once a data migration run by another team is finished. You recalculate the dates of such a dependency in the program view with the “Recalculate dependencies” button. After you check the preview and save, a delay in one project shows in the other project’s schedule. In the program view, the Gantt chart shows the dependencies between projects as arrows.

Try FlexiProject!

Visualize your tasks with FlexiProject Gantt chart – get a full 30-day free access.

FlexiProject

You measure schedule variance against an approved baseline

Trello stores the current card dates, but not the dates the team agreed on at the start, so after a few shifts you cannot measure how far the project has drifted from its original plan. In FlexiProject you record approved dates in the baseline module.

The baseline records the dates from the moment it is sent for approval

You approve the baseline directly or send it through an approval path. The baseline records the schedule as it stood when the plan was sent for approval, and later schedule changes do not alter it, they only show up as variance. On the Gantt chart you display the baseline next to the current schedule, and in the task list you add baseline and variance columns.

You report a date change as a new plan for approval

When a date has to move, you submit a new plan with a justification, the project scope and the alternatives considered, and attach the changed schedule and budget. The plans list shows the project end date and cost for each plan, so the approver sees the scale of the change before the decision. Once approved, the plan replaces the current one, and earlier plans stay on the list.

The Kanban board and the Gantt chart are two views of the same tasks

Moving off Trello does not mean giving up Kanban. In FlexiProject, the project schedule module has three views: a task list, a Gantt chart and a Kanban board. All three use the same data, so a change made in one view shows in the others straight away. The team drags cards between columns as in Trello, while the project manager works on a schedule with dependencies. You group cards by owner, due date, status or any list attribute of the schedule.

Kanban board of project tasks in FlexiProject grouped by owner
Kanban board of project tasks in FlexiProject grouped by owner

FlexiProject vs Trello: scheduling features compared

The table covers scheduling only, while the full comparison of FlexiProject and Trello also includes budgets, risks and portfolios.

FlexiProject Trello
Gantt chart built in Timeline on Premium and Enterprise, Gantt via Power-Ups
Task dependencies four types, also across projects none built in, checklist workaround
Lag between tasks fixed lag in days none
Moving dependent tasks dates recalculated rule shifts dates by the same number of days
Critical path on the Gantt chart none
Baseline approved, with versions none
Kanban board a view of the schedule core view

Moving your schedule from Trello to FlexiProject

On Premium, Trello exports a board to a CSV file. On the free plan it exports to JSON, so you prepare the spreadsheet yourself. FlexiProject imports a schedule from an .xlsx or .csv file: in the data mapping step you assign each column to a task field such as WBS, name, start, end, duration, progress, description or owner e-mail, and columns with matching headers are assigned automatically. After the import you link the tasks with dependencies on the Gantt chart and set the project’s working days.

You do not have to move everything at once. Run projects with a deadline, budget and sponsor in FlexiProject, and keep simple team lists in Trello for now. If you also have plans in Microsoft Project, you import them from an .mpp file together with their dependencies, working days and baselines.

Try FlexiProject!

Try the Gantt chart in FlexiProject. Get 30 days of full, free access to all features

FlexiProject

Frequently asked questions

Does Trello have a Gantt chart?

Trello has a Timeline view on Premium and Enterprise that shows cards with start and due dates. A Gantt chart with dependencies comes from a third-party Power-Up. If you are looking for a Trello alternative for project scheduling, FlexiProject has a built-in Gantt chart module with dependencies, critical path and baseline.

Can you set dependencies between cards in Trello?

Trello has no built-in dependencies. Trello recommends representing them with checklists linked to cards and automation rules. In FlexiProject you create a dependency by dragging from one task bar to another on the Gantt chart.

Does Trello have a baseline or a critical path?

No. Trello stores only the current card dates. In FlexiProject you approve a baseline, compare the current schedule with it and turn on the critical path on the Gantt chart.

Can the team keep working on a Kanban board?

Yes. The Kanban board in FlexiProject is a view of the project schedule. The team drags cards between columns, and the changes show up on the Gantt chart straight away.

Can I import an existing schedule into FlexiProject?

Yes. You import a schedule from an .xlsx or .csv file by mapping columns to task fields, or from a Microsoft Project .mpp file. You prepare Trello data from its CSV export (Premium) or JSON export.

Once a project has an end date and a sequence of work, the checklist, automation and Power-Up workarounds take more and more upkeep. A Trello alternative for project scheduling recalculates dates from dependencies, respects the working-day calendar and shows the critical path. FlexiProject combines these with a baseline approved through an approval path and plan changes that stay in the project history. Your team keeps its Kanban board, because it is just another view of the same tasks. The project manager gets a plan that answers the sponsor’s two questions: when the project will finish and why the date changed.

Łukasz Celeda
Łukasz Celeda
Business Analyst at FlexiProject

Łukasz is a business and systems analyst with extensive experience in designing enterprise software. At FlexiProject, he effectively translates complex requirements into intuitive system features - from initial analysis and UX wireframes to ready-to-use technological solutions. He is a graduate of the Warsaw University of Life Sciences and the Warsaw University of Technology. In his daily work, he focuses on pragmatism, seamlessly combining business, technical, and user perspectives.