{"id":54845,"date":"2026-06-29T16:03:41","date_gmt":"2026-06-29T14:03:41","guid":{"rendered":"https:\/\/flexi-project.com\/?p=54845"},"modified":"2026-07-13T16:53:45","modified_gmt":"2026-07-13T14:53:45","slug":"jak-vytvorit-ganttuv-diagram-v-excelu","status":"publish","type":"post","link":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/","title":{"rendered":"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)"},"content":{"rendered":"<p><strong>Gantt\u016fv diagram prom\u011bn\u00ed seznam \u00fakol\u016f v harmonogram, kter\u00fd se d\u00e1 opravdu \u010d\u00edst: kdo co d\u011bl\u00e1, kdy to za\u010d\u00edn\u00e1 a kdy to kon\u010d\u00ed. Excel je n\u00e1stroj, po kter\u00e9m v\u011bt\u0161ina lid\u00ed s\u00e1hne nejd\u0159\u00edv, a v n\u011bkolika kroc\u00edch v n\u011bm vytvo\u0159\u00edte funk\u010dn\u00ed Gantt\u016fv diagram. Tento n\u00e1vod ukazuje p\u0159esn\u011b, jak na to, od tabulky \u00fakol\u016f po hotov\u00fd diagram. Zab\u00fdv\u00e1 se tak\u00e9 t\u00edm, kde metoda v Excelu p\u0159est\u00e1v\u00e1 sta\u010dit, jak se harmonogram z Excelu importuje rovnou do FlexiProject a jak hotov\u00fd harmonogram zase vyexportovat zp\u011bt do Excelu, PDF nebo Microsoft Project. St\u00e1hn\u011bte si bezplatnou \u0161ablonu n\u00ed\u017ee a poj\u010fte na to.<\/strong><\/p>\n<p><img loading=\"lazy\" decoding=\"async\" class=\"aligncenter size-large wp-image-54770\" src=\"https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step-1024x683.png\" alt=\"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu, krok za krokem, od tabulky \u00fakol\u016f po hotov\u00fd harmonogram\" width=\"1024\" height=\"683\" srcset=\"https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step-1024x683.png 1024w, https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step-300x200.png 300w, https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step-768x512.png 768w, https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png 1536w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/><\/p>\n","protected":false},"excerpt":{"rendered":"<p>Gantt\u016fv diagram v Excelu: n\u00e1vod krok za krokem, jak ho postavit ze skl\u00e1dan\u00e9ho pruhov\u00e9ho grafu, a kde tato metoda kon\u010d\u00ed.<\/p>\n","protected":false},"author":10,"featured_media":54771,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"_yoast_wpseo_meta-robots-noindex":"","footnotes":""},"categories":[589,379],"tags":[],"post_folder":[],"class_list":["post-54845","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-ganttuv-diagram","category-nastroje"],"acf":{"ikonka_strony":"","opis_w_menu":"","nie_pokazuj":false,"sections":[{"acf_fc_layout":"blog_podsumowanie","tresc":"<ul>\n\t<li>Co pot\u0159ebujete, ne\u017e v Excelu vytvo\u0159\u00edte Gantt\u016fv diagram<\/li>\n\t<li>Jak vytvo\u0159it Gantt\u016fv diagram v Excelu v p\u011bti kroc\u00edch<\/li>\n\t<li>Omezen\u00ed <a href=\"https:\/\/flexi-project.com\/cs\/co-je-to-ganttuv-diagram-a-jak-ho-vytvorit-example\/\">Ganttova diagramu<\/a> v Excelu<\/li>\n\t<li>Lep\u0161\u00ed alternativa: Gantt\u016fv diagram ve FlexiProject<\/li>\n\t<li>Jak importovat harmonogram z Excelu a zase ho vyexportovat<\/li>\n<\/ul>"},{"acf_fc_layout":"blog_tresc","tresc":"<h2>Co pot\u0159ebujete k vytvo\u0159en\u00ed Ganttova diagramu v Excelu<\/h2><h3>Tabulka \u00fakol\u016f, na kter\u00e9 stoj\u00ed ka\u017ed\u00fd Gantt\u016fv diagram v Excelu<\/h3>\n<p>Ka\u017ed\u00fd Gantt\u016fv diagram za\u010d\u00edn\u00e1 strukturovan\u00fdmi daty, ne samotn\u00fdm diagramem. Ne\u017e vytvo\u0159\u00edte cokoli vizu\u00e1ln\u00edho, p\u0159ipravte si p\u0159ehlednou tabulku \u00fakol\u016f, proto\u017ee diagram je jen tak dobr\u00fd jako data, kter\u00e1 za n\u00edm stoj\u00ed. P\u00e1te\u0159\u00ed t\u00e9 tabulky je va\u0161e struktura rozpadu prac\u00ed (<a href=\"https:\/\/flexi-project.com\/cs\/co-je-to-work-breakdown-structure-wbs\/\">WBS<\/a>): rozd\u011blte projekt na souhrnn\u00e9 \u00fakoly a pak ka\u017ed\u00fd souhrnn\u00fd \u00fakol rozd\u011blte na men\u0161\u00ed \u00fakoly, kter\u00e9 ho napln\u00ed. Jednoduch\u00fd p\u0159\u00edklad: souhrnn\u00fd \u00fakol \u201e1. N\u00e1vrh\u201c m\u016f\u017ee obsahovat \u201e1.1 N\u00e1vrh rozvr\u017een\u00ed\u201c, \u201e1.2 Intern\u00ed revize\u201c a \u201e1.3 Fin\u00e1ln\u00ed schv\u00e1len\u00ed\u201c. Pr\u00e1v\u011b tato hierarchie \u010din\u00ed harmonogram pozd\u011bji \u010diteln\u00fdm, a\u0165 u\u017e \u017eije v Excelu, nebo kdekoli jinde.<\/p>\n<p>Tabulku za\u010dn\u011bte sloupcem WBS, kter\u00fd tuto strukturu \u010d\u00edsluje (1, 1.1, 1.2, 2, 2.1 a tak d\u00e1le), aby po\u0159ad\u00ed a vztah nad\u0159azen\u00fd\u2013pod\u0159\u00edzen\u00fd byly z\u0159ejm\u00e9 na prvn\u00ed pohled. Pak p\u0159idejte \u010dty\u0159i sloupce, kter\u00e9 odvedou nejv\u00edc pr\u00e1ce: n\u00e1zev \u00fakolu, datum zah\u00e1jen\u00ed, datum dokon\u010den\u00ed a vlastn\u00edk. Samotn\u00fd diagram pot\u0159ebuje je\u0161t\u011b jednu hodnotu, dobu trv\u00e1n\u00ed, co\u017e je prost\u011b po\u010det dn\u00ed mezi datem zah\u00e1jen\u00ed a dokon\u010den\u00ed. Datumy udr\u017eujte ve skute\u010dn\u00e9m form\u00e1tu data, ne jako text, proto\u017ee Excel s nimi mus\u00ed zach\u00e1zet jako s \u010d\u00edsly, aby pruhy spr\u00e1vn\u011b um\u00edstil na \u010dasovou osu.<\/p>\n<p>U souhrnn\u00fdch \u00fakol\u016f plat\u00ed jedno pravidlo: jejich datumy se nezad\u00e1vaj\u00ed, odvozuj\u00ed se. Souhrnn\u00fd \u00fakol za\u010d\u00edn\u00e1 nejd\u0159\u00edv\u011bj\u0161\u00edm datem zah\u00e1jen\u00ed sv\u00fdch pod\u00fakol\u016f a kon\u010d\u00ed nejpozd\u011bj\u0161\u00edm datem dokon\u010den\u00ed sv\u00fdch pod\u00fakol\u016f. Pokud se pod\u00fakol opozd\u00ed, souhrnn\u00fd \u00fakol by se m\u011bl rozt\u00e1hnout, aby to odpov\u00eddalo. V Excelu to udr\u017eujete ru\u010dn\u011b, pomoc\u00ed vzorc\u016f MIN a MAX p\u0159es \u0159\u00e1dky pod\u00fakol\u016f, a je to dal\u0161\u00ed v\u011bc, kterou mus\u00edte dr\u017eet synchronizovanou. P\u0159esn\u011b tut\u00e9\u017e strukturu, WBS, n\u00e1zev, za\u010d\u00e1tek, konec, vlastn\u00edk, o\u010dek\u00e1vaj\u00ed n\u00e1stroje jako FlexiProject, kdy\u017e soubor pozd\u011bji importujete, tak\u017ee se vyplat\u00ed ud\u011blat ji dob\u0159e hned od za\u010d\u00e1tku.<\/p>\n<h3>Bezplatn\u00e1 \u0161ablona Ganttova diagramu v Excelu (ke sta\u017een\u00ed)<\/h3>\n<p>Tabulku nemus\u00edte stav\u011bt z pr\u00e1zdn\u00e9ho listu. Bezplatn\u00e1 \u0161ablona v\u00fd\u0161e u\u017e m\u00e1 nastaven\u00e9 spr\u00e1vn\u00e9 sloupce, WBS, n\u00e1zev \u00fakolu, datum zah\u00e1jen\u00ed, datum dokon\u010den\u00ed, vlastn\u00edka a dobu trv\u00e1n\u00ed, plus funk\u010dn\u00ed skl\u00e1dan\u00fd pruhov\u00fd graf napojen\u00fd na data. Nahra\u010fte vzorov\u00e9 \u0159\u00e1dky vlastn\u00edmi \u00fakoly a graf se aktualizuje s\u00e1m.<\/p>\n<p>\u0160ablona pou\u017e\u00edv\u00e1 rozvr\u017een\u00ed sloupc\u016f, kter\u00e9 se \u010dist\u011b prom\u00edt\u00e1 do projektov\u00e9ho softwaru, tak\u017ee tent\u00fd\u017e soubor, ve kter\u00e9m pl\u00e1nujete, lze pozd\u011bji importovat do FlexiProject bez p\u0159epracov\u00e1n\u00ed. St\u00e1hn\u011bte si ji, vypl\u0148te ji a pou\u017eijte kroky n\u00ed\u017ee, pokud chcete pochopit, jak byla postavena, nebo ji vytvo\u0159it od nuly.<\/p>\n<p style=\"text-align: center; margin-top: 25px; margin-bottom: 25px;\"><a style=\"display: inline-block; padding: 16px 34px; background-color: #1DC9B7; background-image: linear-gradient(135deg, #25d6c3 0%, #15a899 100%); color: #ffffff; font-size: 16px; font-weight: 600; text-decoration: none; border-radius: 30px; box-shadow: 0 4px 12px rgba(29,201,183,0.35);\" href=\"https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/Gantt-Chart-Template-FlexiProject.xlsx\" download=\"Gantt-Chart-Template-FlexiProject.xlsx\"><span style=\"color: #ffffff;\">&#11015; St\u00e1hnout bezplatnou \u0161ablonu Ganttova diagramu v Excelu<\/span><\/a><\/p>"},{"acf_fc_layout":"blog_tresc","tresc":"<h2>Jak vytvo\u0159it Gantt\u016fv diagram v Excelu: 5 krok\u016f<\/h2><h3>Krok 1: postavte tabulku \u00fakol\u016f (WBS, datumy, vlastn\u00edk)<\/h3>\n<p>Otev\u0159ete pr\u00e1zdn\u00fd list a vytvo\u0159te \u0161est sloupc\u016f: WBS, \u00dakol, Datum zah\u00e1jen\u00ed, Datum dokon\u010den\u00ed, Vlastn\u00edk a Doba trv\u00e1n\u00ed. Ve sloupci WBS o\u010d\u00edslujte svou strukturu (1, 1.1, 1.2, 2 a tak d\u00e1le) a zadejte \u00fakoly v tomto po\u0159ad\u00ed, nejd\u0159\u00edv souhrnn\u00e9 \u00fakoly s jejich pod\u00fakoly uveden\u00fdmi pod nimi. Ve sloupci Doba trv\u00e1n\u00ed ode\u010dt\u011bte datum zah\u00e1jen\u00ed od data dokon\u010den\u00ed, aby Excel vr\u00e1til po\u010det dn\u00ed. U \u0159\u00e1dk\u016f souhrnn\u00fdch \u00fakol\u016f pou\u017eijte MIN dat zah\u00e1jen\u00ed pod\u00fakol\u016f a MAX dat dokon\u010den\u00ed m\u00edsto ru\u010dn\u00edho zad\u00e1v\u00e1n\u00ed datum\u016f. Ujist\u011bte se, \u017ee bu\u0148ky s daty jsou naform\u00e1tovan\u00e9 jako data, ne jako text, jinak se graf nevykresl\u00ed spr\u00e1vn\u011b.<\/p>\n<h3>Krok 2: vlo\u017ete skl\u00e1dan\u00fd pruhov\u00fd graf<\/h3>\n<p>Ozna\u010dte sloupce \u00dakol a Datum zah\u00e1jen\u00ed, pak otev\u0159ete kartu Vlo\u017een\u00ed a vyberte 2D skl\u00e1dan\u00fd pruhov\u00fd graf. Excel nem\u00e1 vyhrazen\u00fd typ Ganttova diagramu, tak\u017ee tento skl\u00e1dan\u00fd pruh je z\u00e1klad, kter\u00fd teprve vytvarujete. D\u00e1le p\u0159idejte sloupec Doba trv\u00e1n\u00ed jako druhou datovou \u0159adu, tak\u017ee ka\u017ed\u00fd \u0159\u00e1dek te\u010f ukazuje dva skl\u00e1dan\u00e9 segmenty: posun za\u010d\u00e1tku a d\u00e9lku \u00fakolu.<\/p>\n<h3>Krok 3: skryjte \u0159adu s datem zah\u00e1jen\u00ed<\/h3>\n<p>To je trik, kter\u00fd prom\u011bn\u00ed oby\u010dejn\u00fd pruhov\u00fd graf v Gantt\u016fv diagram. Klikn\u011bte na prvn\u00ed \u0159adu, tu zalo\u017eenou na datu zah\u00e1jen\u00ed, otev\u0159ete mo\u017enosti v\u00fdpln\u011b a nastavte Bez v\u00fdpln\u011b. Segment data zah\u00e1jen\u00ed se stane neviditeln\u00fdm a z\u016fstane pruh doby trv\u00e1n\u00ed, kter\u00fd jako by se vzn\u00e1\u0161el a za\u010d\u00ednal ve spr\u00e1vn\u00e9m datu. Opakujte to u ohrani\u010den\u00ed, pokud je je\u0161t\u011b vid\u011bt n\u011bjak\u00e1 \u010d\u00e1ra.<\/p>\n<h3>Krok 4: obra\u0165te po\u0159ad\u00ed \u00fakol\u016f a opravte osu dat<\/h3>\n<p>Ve v\u00fdchoz\u00edm nastaven\u00ed Excel um\u00edst\u00ed prvn\u00ed \u00fakol dol\u016f. Otev\u0159ete mo\u017enosti svisl\u00e9 osy a za\u0161krtn\u011bte \u201eKategorie v obr\u00e1cen\u00e9m po\u0159ad\u00ed\u201c, aby se va\u0161e \u00fakoly \u010detly shora dol\u016f, jak to u Ganttova diagramu m\u00e1 b\u00fdt. Pak upravte vodorovnou osu dat: nastavte minim\u00e1ln\u00ed a maxim\u00e1ln\u00ed meze na datum zah\u00e1jen\u00ed a dokon\u010den\u00ed projektu, aby pruhy vyplnily graf m\u00edsto toho, aby se ma\u010dkaly do rohu. Excel ukl\u00e1d\u00e1 data jako po\u0159adov\u00e1 \u010d\u00edsla, tak\u017ee tyto meze mo\u017en\u00e1 budete muset zadat jako \u010d\u00edsla.<\/p>\n<h3>Krok 5: naform\u00e1tujte Gantt\u016fv diagram<\/h3>\n<p>V\u00fdsledek upravte. Zmen\u0161ete \u0161\u00ed\u0159ku mezery, aby pruhy vypadaly jako po\u0159\u00e1dn\u00e1 \u010dasov\u00e1 osa, obarv\u011bte pruhy doby trv\u00e1n\u00ed, p\u0159idejte popisky dat nebo n\u00e1zvy \u00fakol\u016f, pokud pom\u00e1haj\u00ed, a vy\u010dist\u011bte m\u0159\u00ed\u017eku. Pokud chcete uk\u00e1zat pr\u016fb\u011bh, n\u011bkte\u0159\u00ed p\u0159id\u00e1vaj\u00ed t\u0159et\u00ed, tmav\u0161\u00ed \u0159adu o velikosti odpov\u00eddaj\u00edc\u00ed procentu dokon\u010den\u00ed, i kdy\u017e to p\u0159id\u00e1v\u00e1 dal\u0161\u00ed ru\u010dn\u00ed \u00fadr\u017ebu. V tomto bod\u011b m\u00e1te \u010diteln\u00fd Gantt\u016fv diagram v Excelu.<\/p>"},{"acf_fc_layout":"cta","styl":"srodek","motyw":"dark","wybor_klasy_przycisku":"btn_blue","tlo":"bg-clean","uklad_tla":"prostokat","subtytul":"FlexiProject","wyroznione_slowo":"","desc":"Dr\u017ete harmonogram! Vyzkou\u0161ejte Gantt\u016fv diagram ve FlexiProject s 30 dny p\u0159\u00edstupu zdarma.","zdjecie":null,"pokaz_srodowisko":true,"pokaz_kontakt":false,"glowny_przycisk":"env"},{"acf_fc_layout":"blog_tresc","tresc":"<h2>Omezen\u00ed Ganttova diagramu v Excelu<\/h2><h3>\u017d\u00e1dn\u00e9 z\u00e1vislosti mezi \u00fakoly ani kritick\u00e1 cesta v Excelu<\/h3>\n<p>Gantt\u016fv diagram v Excelu je obr\u00e1zek, ne harmonogram. Pruhy o sob\u011b navz\u00e1jem nev\u011bd\u00ed. Pokud \u00fakol B m\u016f\u017ee za\u010d\u00edt a\u017e po dokon\u010den\u00ed \u00fakolu A, Excel to nevynut\u00ed a \u00fakol B neposune, kdy\u017e se \u00fakol A opozd\u00ed. Nen\u00ed tu ani kritick\u00e1 cesta: Excel neum\u00ed spo\u010d\u00edtat, kter\u00fd \u0159et\u011bzec \u00fakol\u016f vlastn\u011b ur\u010duje va\u0161e datum dokon\u010den\u00ed, co\u017e je ta neju\u017eite\u010dn\u011bj\u0161\u00ed v\u011bc, kterou v\u00e1m skute\u010dn\u00fd harmonogram \u0159ekne.<\/p>\n<h3>Ru\u010dn\u00ed aktualizace, kter\u00e9 se p\u0159i \u0161k\u00e1lov\u00e1n\u00ed hrout\u00ed<\/h3>\n<p>Prvn\u00ed graf pot\u011b\u0161\u00ed. Des\u00e1t\u00e1 aktualizace ne. Poka\u017ed\u00e9, kdy\u017e se zm\u011bn\u00ed datum, upravujete tabulku, znovu kontrolujete vzorec doby trv\u00e1n\u00ed a \u010dasto znovu dolad\u00edte meze osy a form\u00e1tov\u00e1n\u00ed. U pl\u00e1nu na p\u011bt \u00fakol\u016f je to v pohod\u011b. U projektu na pades\u00e1t \u00fakol\u016f, kter\u00fd se m\u011bn\u00ed ka\u017ed\u00fd t\u00fdden, se z toho stane pr\u00e1ce na p\u016fl \u00favazku, a ka\u017ed\u00e1 ru\u010dn\u00ed \u00faprava je p\u0159\u00edle\u017eitost\u00ed zan\u00e9st chybu, kter\u00e9 si nikdo nev\u0161imne, dokud neza\u010dne hr\u00e1t roli.<\/p>\n<h3>\u017d\u00e1dn\u00e9 miln\u00edky, p\u0159\u00edlohy ani koment\u00e1\u0159e<\/h3>\n<p>Seri\u00f3zn\u00ed harmonogram nese v\u00edc ne\u017e pruhy. M\u00e1 <a href=\"https:\/\/flexi-project.com\/cs\/milniky-v-rizeni-projektu\/\">miln\u00edky<\/a> pro vyzna\u010den\u00ed kl\u00ed\u010dov\u00fdch rozhodovac\u00edch bod\u016f, p\u0159\u00edlohy, aby specifikace nebo v\u00fdkres sed\u011bly u \u00fakolu, ke kter\u00e9mu pat\u0159\u00ed, a koment\u00e1\u0159e, aby t\u00fdm mohl \u00fakol probrat v kontextu. Excel v\u00e1m d\u00e1 bu\u0148ku a graf. Nen\u00ed tu p\u0159irozen\u00e9 m\u00edsto, kam p\u0159ipnout miln\u00edk, p\u0159ipojit soubor ke konkr\u00e9tn\u00edmu \u00fakolu nebo v\u00e9st rozhovor o tom, pro\u010d se datum posunulo.<\/p>\n<h3>\u017d\u00e1dn\u00e1 upozorn\u011bn\u00ed ani pohled nap\u0159\u00ed\u010d projekty<\/h3>\n<p>Excel nikomu nikdy ne\u0159ekne, \u017ee \u00fakol m\u00e1 term\u00edn z\u00edtra nebo je u\u017e po term\u00ednu; soubor tam jen le\u017e\u00ed, dokud ho n\u011bkdo neotev\u0159e. A proto\u017ee ka\u017ed\u00fd projekt \u017eije ve vlastn\u00edm se\u0161itu, nen\u00ed tu jedin\u00e9 m\u00edsto, kde vid\u011bt \u00fakoly z n\u011bkolika projekt\u016f najednou. Ve chv\u00edli, kdy vedete v\u00edc ne\u017e jeden projekt nebo pracujete s t\u00fdmem, kter\u00fd pot\u0159ebuje p\u0159ipom\u00ednky, tabulka p\u0159est\u00e1v\u00e1 sta\u010dit.<\/p>"},{"acf_fc_layout":"blog_tresc","tresc":"<h2>Lep\u0161\u00ed alternativa k Ganttovu diagramu v Excelu: FlexiProject<\/h2><h3>Intuitivn\u00ed Gantt\u016fv diagram, bez trik\u016f s form\u00e1tov\u00e1n\u00edm<\/h3>\n<p>FlexiProject p\u0159ich\u00e1z\u00ed s Ganttov\u00fdm diagramem, tak\u017ee \u017e\u00e1dn\u00e9 obch\u00e1zen\u00ed skl\u00e1dan\u00fdm pruhem ani \u017e\u00e1dn\u00e1 neviditeln\u00e1 \u0159ada k \u00fadr\u017eb\u011b. \u00dakol p\u0159et\u00e1hnete, abyste ho posunuli na \u010dasov\u00e9 ose, p\u0159et\u00e1hnete jeho okraj, abyste zm\u011bnili dobu trv\u00e1n\u00ed, a p\u0159et\u00e1hnete \u00fachyt, abyste nastavili pr\u016fb\u011bh, a datumy se aktualizuj\u00ed okam\u017eit\u011b. Z\u00e1vislosti nejsou vzorec; my\u0161\u00ed nakresl\u00edte \u010d\u00e1ru z jednoho \u00fakolu na druh\u00fd a harmonogram ji respektuje. Jedin\u00fd p\u0159ep\u00edna\u010d p\u0159ekryje kritickou cestu, linii dne\u0161ka, miln\u00edky a vyt\u00ed\u017een\u00ed <a href=\"\/cs\/zdroje\/\">zdroj\u016f<\/a>, a hromadn\u00e1 \u00faprava v\u00e1m umo\u017en\u00ed zm\u011bnit vlastn\u00edky nebo datumy u mnoha \u00fakol\u016f najednou. Jin\u00fdmi slovy, v\u0161echno, co metoda v Excelu neum\u00ed, je tu v\u00fdchoz\u00ed.<\/p>"},{"acf_fc_layout":"cta","styl":"srodek","motyw":"dark","wybor_klasy_przycisku":"btn_blue","tlo":"bg-clean","uklad_tla":"prostokat","subtytul":"FlexiProject","wyroznione_slowo":"","desc":"Vizualizujte sv\u00e9 \u00fakoly v Ganttov\u011b diagramu FlexiProject, z\u00edskejte pln\u00fdch 30 dn\u00ed p\u0159\u00edstupu zdarma.","zdjecie":null,"pokaz_srodowisko":true,"pokaz_kontakt":false,"glowny_przycisk":"env"},{"acf_fc_layout":"blog_tresc","tresc":"<h2>P\u0159esu\u0148te sv\u016fj harmonogram do FlexiProject a zp\u011bt<\/h2><h3>Importujte sv\u016fj Gantt\u016fv diagram z Excelu do FlexiProject<\/h3>\n<p>O pr\u00e1ci, kterou jste vlo\u017eili do Excelu, nep\u0159ijdete. FlexiProject importuje v\u00e1\u0161 se\u0161it p\u0159\u00edmo: p\u0159ejd\u011bte na kartu Projekty, klikn\u011bte na Nov\u00fd projekt a vyberte \u201eZ Microsoft Excel\u201c. P\u0159ipojte sv\u016fj soubor, pak namapujte ka\u017ed\u00fd sloupec na odpov\u00eddaj\u00edc\u00ed pole, n\u00e1zev \u00fakolu, za\u010d\u00e1tek, konec, vlastn\u00edk, a p\u0159esko\u010dte to, co nepot\u0159ebujete. Nastavte form\u00e1t data, pokud Excel pou\u017eil region\u00e1ln\u00ed, vyberte funkce, kter\u00e9 chcete, a syst\u00e9m z va\u0161ich dat postav\u00ed \u017eiv\u00fd projekt a otev\u0159e ho v harmonogramu. P\u0159ehledn\u00e1 tabulka \u00fakol\u016f z Kroku 1 je p\u0159esn\u011b to, co toto mapov\u00e1n\u00ed d\u011bl\u00e1 bezbolestn\u00fdm.<\/p>\n<div style=\"position: relative; width: 100%; max-width: 760px; margin: 25px auto; padding-bottom: 56.25%; height: 0; overflow: hidden; border-radius: 12px;\"><iframe style=\"position: absolute; top: 0; left: 0; width: 100%; height: 100%; border: 0;\" src=\"https:\/\/www.youtube.com\/embed\/Z-9S6HW_xHc\" title=\"Import Ganttova diagramu z Excelu do FlexiProject\" frameborder=\"0\" allow=\"accelerometer; autoplay; clipboard-write; encrypted-media; gyroscope; picture-in-picture; web-share\" allowfullscreen><\/iframe><\/div>\n<p>U\u017e pracujete v Microsoft Project? Tent\u00fd\u017e postup zvl\u00e1dne soubory .mpp p\u0159es mo\u017enost \u201eZ Microsoft Project\u201c a namapuje N\u00e1zev, Za\u010d\u00e1tek, Konec a P\u0159edch\u016fdce, tak\u017ee se p\u0159enesou i va\u0161e z\u00e1vislosti.<\/p>\n<div style=\"position: relative; width: 100%; max-width: 760px; margin: 25px auto; padding-bottom: 56.25%; height: 0; overflow: hidden; border-radius: 12px;\"><iframe style=\"position: absolute; top: 0; left: 0; width: 100%; height: 100%; border: 0;\" src=\"https:\/\/www.youtube.com\/embed\/3WmYmqcc_s8\" title=\"Import souboru Microsoft Project do FlexiProject\" frameborder=\"0\" allow=\"accelerometer; autoplay; clipboard-write; encrypted-media; gyroscope; picture-in-picture; web-share\" allowfullscreen><\/iframe><\/div>\n<h3>Exportujte z FlexiProject do Excelu, PDF, PNG a Microsoft Project<\/h3>\n<p>Pr\u00e1ce ve FlexiProject va\u0161e data nezamyk\u00e1. Ze seznamu harmonogramu m\u016f\u017eete cel\u00fd harmonogram vyexportovat do souboru Excel nebo do souboru XML, kter\u00fd se otev\u0159e v Microsoft Project. Z pohledu Ganttova diagramu m\u016f\u017eete \u010dasovou osu vyexportovat jako PDF pro reporty a archivaci, jako PNG pro vlo\u017een\u00ed do prezentace, nebo jako XML pro Microsoft Project. Export zachov\u00e1 v\u00e1\u0161 aktu\u00e1ln\u00ed pohled, v\u010detn\u011b filtr\u016f a p\u0159ibl\u00ed\u017een\u00ed, tak\u017ee to, co ode\u0161lete, je to, co vid\u00edte.<\/p>"},{"acf_fc_layout":"cta","styl":"srodek","motyw":"dark","wybor_klasy_przycisku":"btn_blue","tlo":"bg-clean","uklad_tla":"prostokat","subtytul":"FlexiProject","wyroznione_slowo":"","desc":"Prozkoumejte Gantt\u016fv diagram ve FlexiProject, 30 dn\u00ed zdarma s pln\u00fdm p\u0159\u00edstupem!","zdjecie":null,"pokaz_srodowisko":true,"pokaz_kontakt":false,"glowny_przycisk":"env"},{"acf_fc_layout":"blog_tresc","tresc":"<h2>Gantt\u016fv diagram v Excelu: \u010dast\u00e9 dotazy<\/h2><h3>M\u00e1 Excel vestav\u011bn\u00fd Gantt\u016fv diagram?<\/h3>\n<p>Ne. Excel nem\u00e1 vyhrazen\u00fd typ Ganttova diagramu. Vytvo\u0159\u00edte ho tak, \u017ee postav\u00edte skl\u00e1dan\u00fd pruhov\u00fd graf a \u0159adu s datem zah\u00e1jen\u00ed ud\u011bl\u00e1te neviditelnou, jak je pops\u00e1no v kroc\u00edch v\u00fd\u0161e. Funguje to, ale je to obejit\u00ed, ne \u00fa\u010delov\u011b vytvo\u0159en\u00e1 funkce.<\/p>\n<h3>Lze v Ganttov\u011b diagramu v Excelu zobrazit z\u00e1vislosti mezi \u00fakoly?<\/h3>\n<p>Ne automaticky. \u0160ipky m\u016f\u017eete nakreslit ru\u010dn\u011b, ale Excel \u00fakoly nepropoj\u00ed ani neposune z\u00e1visl\u00fd \u00fakol, kdy\u017e se zm\u011bn\u00ed jeho p\u0159edch\u016fdce. Pro skute\u010dn\u00e9 z\u00e1vislosti a vypo\u010d\u00edtanou kritickou cestu pot\u0159ebujete pl\u00e1novac\u00ed software vytvo\u0159en\u00fd p\u0159esn\u011b pro to.<\/p>\n<h3>Jak importuji harmonogram z Excelu do projektov\u00e9ho softwaru?<\/h3>\n<p>Ve FlexiProject p\u0159ejd\u011bte na Projekty, klikn\u011bte na Nov\u00fd projekt a vyberte \u201eZ Microsoft Excel\u201c. Nahrajte soubor, namapujte ka\u017ed\u00fd sloupec (n\u00e1zev \u00fakolu, za\u010d\u00e1tek, konec, vlastn\u00edk) na odpov\u00eddaj\u00edc\u00ed pole a syst\u00e9m z va\u0161eho se\u0161itu vytvo\u0159\u00ed \u017eiv\u00fd projekt.<\/p>\n<h3>M\u016f\u017eu vyexportovat Gantt\u016fv diagram z FlexiProject do Excelu nebo PDF?<\/h3>\n<p>Ano. Seznam harmonogramu se exportuje do Excelu nebo do XML Microsoft Project a pohled Ganttova diagramu se exportuje do PDF, PNG nebo XML. Exportovan\u00fd soubor zachov\u00e1 va\u0161e aktu\u00e1ln\u00ed filtry a \u00farove\u0148 p\u0159ibl\u00ed\u017een\u00ed.<\/p>\n<h3>Sta\u010d\u00ed Excel na pl\u00e1nov\u00e1n\u00ed projekt\u016f?<\/h3>\n<p>Pro mal\u00fd, stabiln\u00ed pl\u00e1n sta\u010dit m\u016f\u017ee. Jakmile m\u00e1te z\u00e1vislosti, miln\u00edky, t\u00fdm, kter\u00fd pot\u0159ebuje upozorn\u011bn\u00ed, nebo n\u011bkolik projekt\u016f ke sledov\u00e1n\u00ed najednou, ru\u010dn\u00ed tabulka p\u0159est\u00e1v\u00e1 sta\u010dit a vyhrazen\u00fd n\u00e1stroj u\u0161et\u0159\u00ed v\u00edc \u010dasu, ne\u017e kolik stoj\u00ed.<\/p>"},{"acf_fc_layout":"blog_tresc","tresc":"<h2>Od rychl\u00e9ho diagramu k \u017eiv\u00e9mu harmonogramu<\/h2><p>Sestavit Gantt\u016fv diagram v Excelu je u\u017eite\u010dn\u00e1 dovednost a pro rychl\u00fd, jednor\u00e1zov\u00fd pohled svou pr\u00e1ci odvede. Metoda je jednoduch\u00e1, jakmile zn\u00e1te trik se skl\u00e1dan\u00fdm pruhem: zstrukturujte \u00fakoly pomoc\u00ed WBS, vypl\u0148te n\u00e1zvy, datumy a vlastn\u00edky a odtud diagram vytvarujte. Co Excel neum\u00ed, je udr\u017eet ten harmonogram na\u017eivu. Z\u00e1vislosti, kritick\u00e1 cesta, miln\u00edky, p\u0159\u00edlohy, upozorn\u011bn\u00ed a pohled nap\u0159\u00ed\u010d projekty le\u017e\u00ed mimo jeho dosah. To je hranice, kde si vyhrazen\u00fd n\u00e1stroj zaslou\u017e\u00ed sv\u00e9 m\u00edsto. S FlexiProject nakresl\u00edte tent\u00fd\u017e harmonogram jednou, graf se udr\u017euje s\u00e1m a data m\u016f\u017eete p\u0159esouvat z Excelu nebo ven do Excelu, PDF a Microsoft Project, kdykoli pot\u0159ebujete. Pokud u\u017e se\u0161it m\u00e1te, importujte ho a uvid\u00edte rozd\u00edl na vlastn\u00edm projektu.<\/p>"}],"hide_all":false,"hide_more":false,"wybor_autora":[2001]},"yoast_head":"<!-- This site is optimized with the Yoast SEO Premium plugin v28.9 (Yoast SEO v28.9) - https:\/\/yoast.com\/product\/yoast-seo-premium-wordpress\/ -->\n<title>Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)<\/title>\n<meta name=\"description\" content=\"Gantt\u016fv diagram v Excelu: n\u00e1vod krok za krokem, jak ho vytvo\u0159it, a kde tato metoda p\u0159est\u00e1v\u00e1 sta\u010dit.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/\" \/>\n<meta property=\"og:locale\" content=\"cs_CZ\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)\" \/>\n<meta property=\"og:description\" content=\"Gantt\u016fv diagram v Excelu: n\u00e1vod krok za krokem, jak ho vytvo\u0159it, a kde tato metoda p\u0159est\u00e1v\u00e1 sta\u010dit.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/\" \/>\n<meta property=\"og:site_name\" content=\"FlexiProject\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/FlexiProject\" \/>\n<meta property=\"article:published_time\" content=\"2026-06-29T14:03:41+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-07-13T14:53:45+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png\" \/>\n\t<meta property=\"og:image:width\" content=\"1536\" \/>\n\t<meta property=\"og:image:height\" content=\"1024\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Dominik Wrzosek\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Napsal(a)\" \/>\n\t<meta name=\"twitter:data1\" content=\"Klaudiusz\" \/>\n\t<meta name=\"twitter:label2\" content=\"Odhadovan\u00e1 doba \u010dten\u00ed\" \/>\n\t<meta name=\"twitter:data2\" content=\"1 minuta\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/\"},\"author\":{\"name\":\"Dominik Wrzosek\",\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/#\\\/schema\\\/person\\\/044e0f4796374a2150016ce18f18503d\"},\"headline\":\"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)\",\"datePublished\":\"2026-06-29T14:03:41+00:00\",\"dateModified\":\"2026-07-13T14:53:45+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/\"},\"wordCount\":1826,\"publisher\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/flexi-project.com\\\/wp-content\\\/uploads\\\/2026\\\/06\\\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png\",\"articleSection\":[\"Gantt\u016fv diagram\",\"N\u00e1stroje\"],\"inLanguage\":\"cs\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/\",\"url\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/\",\"name\":\"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/flexi-project.com\\\/wp-content\\\/uploads\\\/2026\\\/06\\\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png\",\"datePublished\":\"2026-06-29T14:03:41+00:00\",\"dateModified\":\"2026-07-13T14:53:45+00:00\",\"description\":\"Gantt\u016fv diagram v Excelu: n\u00e1vod krok za krokem, jak ho vytvo\u0159it, a kde tato metoda p\u0159est\u00e1v\u00e1 sta\u010dit.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/#breadcrumb\"},\"inLanguage\":\"cs\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"cs\",\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/#primaryimage\",\"url\":\"https:\\\/\\\/flexi-project.com\\\/wp-content\\\/uploads\\\/2026\\\/06\\\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png\",\"contentUrl\":\"https:\\\/\\\/flexi-project.com\\\/wp-content\\\/uploads\\\/2026\\\/06\\\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png\",\"width\":1536,\"height\":1024,\"caption\":\"Gantt\u016fv diagram sestaven\u00fd z barevn\u00fdch bun\u011bk v tabulce Excel, se z\u00e1vislostmi \u00fakol\u016f\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/jak-vytvorit-ganttuv-diagram-v-excelu\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Dom\u016f\",\"item\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Gantt\u016fv diagram\",\"item\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/category\\\/ganttuv-diagram\\\/\"},{\"@type\":\"ListItem\",\"position\":3,\"name\":\"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/#website\",\"url\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/\",\"name\":\"FlexiProject\",\"description\":\"Project and porfolio management software | FlexiProject\",\"publisher\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/#organization\"},\"alternateName\":\"FlexiProject\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"cs\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/#organization\",\"name\":\"FlexiProject\",\"alternateName\":\"FlexiProject\",\"url\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"cs\",\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/flexi-project.com\\\/wp-content\\\/uploads\\\/2024\\\/02\\\/FlexiProject_logo_814px.png\",\"contentUrl\":\"https:\\\/\\\/flexi-project.com\\\/wp-content\\\/uploads\\\/2024\\\/02\\\/FlexiProject_logo_814px.png\",\"width\":982,\"height\":1007,\"caption\":\"FlexiProject\"},\"image\":{\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/FlexiProject\",\"https:\\\/\\\/www.instagram.com\\\/flexiproject\\\/\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/flexiproject\\\/\",\"https:\\\/\\\/www.youtube.com\\\/@flexiproject\"],\"description\":\"FlexiProject to kompleksowy program do zarz\u0105dzania projektami i portfelami projekt\u00f3w. Oferuje zespo\u0142om projektowych kompletny zestaw narz\u0119dzi, kt\u00f3re pozwalaj\u0105 zaplanowa\u0107 i skutecznie zrealizowa\u0107 dowolny projekt w organizacji, niezale\u017cnie od rozmiaru czy stopnia zaawansowania.\",\"telephone\":\"+48 22 351 13 82\",\"legalName\":\"FlexiProject Sp. z o.o. Sp.k.\",\"foundingDate\":\"2020-11-26\",\"vatID\":\"5272942612\",\"taxID\":\"387620990\",\"numberOfEmployees\":{\"@type\":\"QuantitativeValue\",\"minValue\":\"11\",\"maxValue\":\"50\"},\"ownershipFundingInfo\":\"https:\\\/\\\/flexi-project.com\\\/pl\\\/key-strengths\\\/\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/flexi-project.com\\\/cs\\\/#\\\/schema\\\/person\\\/044e0f4796374a2150016ce18f18503d\",\"name\":\"Dominik Wrzosek\",\"description\":\"Dominik je odborn\u00edk na \u0159\u00edzen\u00ed projekt\u016f a absolvent Var\u0161avsk\u00e9 polytechniky. \u0158\u00edd\u00ed v\u00fdvoj syst\u00e9mu FlexiProject a p\u0159ev\u00e1d\u00ed obchodn\u00ed pot\u0159eby do praktick\u00fdch \u0159e\u0161en\u00ed podporuj\u00edc\u00edch projektov\u00e9 t\u00fdmy. M\u00e1 zku\u0161enosti s implementac\u00ed FlexiProject v organizac\u00edch r\u016fzn\u00e9 velikosti a kombinuje technick\u00e9 znalosti s obchodn\u00edm p\u0159\u00edstupem k efektivn\u00edmu pl\u00e1nov\u00e1n\u00ed a realizaci projekt\u016f.\",\"jobTitle\":\"General Manager at FlexiProject\",\"sameAs\":[\"https:\\\/\\\/www.linkedin.com\\\/in\\\/dominik-wrzosek-929425140\\\/\"],\"image\":{\"@type\":\"ImageObject\",\"url\":\"https:\\\/\\\/flexi-project.com\\\/wp-content\\\/uploads\\\/2024\\\/03\\\/Dominik-Wrzosek-2.jpg\",\"contentUrl\":\"https:\\\/\\\/flexi-project.com\\\/wp-content\\\/uploads\\\/2024\\\/03\\\/Dominik-Wrzosek-2.jpg\"}}]}<\/script>\n<!-- \/ Yoast SEO Premium plugin. -->","yoast_head_json":{"title":"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)","description":"Gantt\u016fv diagram v Excelu: n\u00e1vod krok za krokem, jak ho vytvo\u0159it, a kde tato metoda p\u0159est\u00e1v\u00e1 sta\u010dit.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/","og_locale":"cs_CZ","og_type":"article","og_title":"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)","og_description":"Gantt\u016fv diagram v Excelu: n\u00e1vod krok za krokem, jak ho vytvo\u0159it, a kde tato metoda p\u0159est\u00e1v\u00e1 sta\u010dit.","og_url":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/","og_site_name":"FlexiProject","article_publisher":"https:\/\/www.facebook.com\/FlexiProject","article_published_time":"2026-06-29T14:03:41+00:00","article_modified_time":"2026-07-13T14:53:45+00:00","og_image":[{"width":1536,"height":1024,"url":"https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png","type":"image\/png"}],"author":"Dominik Wrzosek","twitter_card":"summary_large_image","twitter_misc":{"Napsal(a)":"Klaudiusz","Odhadovan\u00e1 doba \u010dten\u00ed":"1 minuta"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/#article","isPartOf":{"@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/"},"author":{"name":"Dominik Wrzosek","@id":"https:\/\/flexi-project.com\/cs\/#\/schema\/person\/044e0f4796374a2150016ce18f18503d"},"headline":"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)","datePublished":"2026-06-29T14:03:41+00:00","dateModified":"2026-07-13T14:53:45+00:00","mainEntityOfPage":{"@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/"},"wordCount":1826,"publisher":{"@id":"https:\/\/flexi-project.com\/cs\/#organization"},"image":{"@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/#primaryimage"},"thumbnailUrl":"https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png","articleSection":["Gantt\u016fv diagram","N\u00e1stroje"],"inLanguage":"cs"},{"@type":"WebPage","@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/","url":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/","name":"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)","isPartOf":{"@id":"https:\/\/flexi-project.com\/cs\/#website"},"primaryImageOfPage":{"@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/#primaryimage"},"image":{"@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/#primaryimage"},"thumbnailUrl":"https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png","datePublished":"2026-06-29T14:03:41+00:00","dateModified":"2026-07-13T14:53:45+00:00","description":"Gantt\u016fv diagram v Excelu: n\u00e1vod krok za krokem, jak ho vytvo\u0159it, a kde tato metoda p\u0159est\u00e1v\u00e1 sta\u010dit.","breadcrumb":{"@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/#breadcrumb"},"inLanguage":"cs","potentialAction":[{"@type":"ReadAction","target":["https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/"]}]},{"@type":"ImageObject","inLanguage":"cs","@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/#primaryimage","url":"https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png","contentUrl":"https:\/\/flexi-project.com\/wp-content\/uploads\/2026\/06\/How-to-make-a-Gantt-chart-in-Excel-step-by-step.png","width":1536,"height":1024,"caption":"Gantt\u016fv diagram sestaven\u00fd z barevn\u00fdch bun\u011bk v tabulce Excel, se z\u00e1vislostmi \u00fakol\u016f"},{"@type":"BreadcrumbList","@id":"https:\/\/flexi-project.com\/cs\/jak-vytvorit-ganttuv-diagram-v-excelu\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Dom\u016f","item":"https:\/\/flexi-project.com\/cs\/"},{"@type":"ListItem","position":2,"name":"Gantt\u016fv diagram","item":"https:\/\/flexi-project.com\/cs\/category\/ganttuv-diagram\/"},{"@type":"ListItem","position":3,"name":"Jak vytvo\u0159it Gantt\u016fv diagram v Excelu (krok za krokem)"}]},{"@type":"WebSite","@id":"https:\/\/flexi-project.com\/cs\/#website","url":"https:\/\/flexi-project.com\/cs\/","name":"FlexiProject","description":"Project and porfolio management software | FlexiProject","publisher":{"@id":"https:\/\/flexi-project.com\/cs\/#organization"},"alternateName":"FlexiProject","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/flexi-project.com\/cs\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"cs"},{"@type":"Organization","@id":"https:\/\/flexi-project.com\/cs\/#organization","name":"FlexiProject","alternateName":"FlexiProject","url":"https:\/\/flexi-project.com\/cs\/","logo":{"@type":"ImageObject","inLanguage":"cs","@id":"https:\/\/flexi-project.com\/cs\/#\/schema\/logo\/image\/","url":"https:\/\/flexi-project.com\/wp-content\/uploads\/2024\/02\/FlexiProject_logo_814px.png","contentUrl":"https:\/\/flexi-project.com\/wp-content\/uploads\/2024\/02\/FlexiProject_logo_814px.png","width":982,"height":1007,"caption":"FlexiProject"},"image":{"@id":"https:\/\/flexi-project.com\/cs\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/FlexiProject","https:\/\/www.instagram.com\/flexiproject\/","https:\/\/www.linkedin.com\/company\/flexiproject\/","https:\/\/www.youtube.com\/@flexiproject"],"description":"FlexiProject to kompleksowy program do zarz\u0105dzania projektami i portfelami projekt\u00f3w. Oferuje zespo\u0142om projektowych kompletny zestaw narz\u0119dzi, kt\u00f3re pozwalaj\u0105 zaplanowa\u0107 i skutecznie zrealizowa\u0107 dowolny projekt w organizacji, niezale\u017cnie od rozmiaru czy stopnia zaawansowania.","telephone":"+48 22 351 13 82","legalName":"FlexiProject Sp. z o.o. Sp.k.","foundingDate":"2020-11-26","vatID":"5272942612","taxID":"387620990","numberOfEmployees":{"@type":"QuantitativeValue","minValue":"11","maxValue":"50"},"ownershipFundingInfo":"https:\/\/flexi-project.com\/pl\/key-strengths\/"},{"@type":"Person","@id":"https:\/\/flexi-project.com\/cs\/#\/schema\/person\/044e0f4796374a2150016ce18f18503d","name":"Dominik Wrzosek","description":"Dominik je odborn\u00edk na \u0159\u00edzen\u00ed projekt\u016f a absolvent Var\u0161avsk\u00e9 polytechniky. \u0158\u00edd\u00ed v\u00fdvoj syst\u00e9mu FlexiProject a p\u0159ev\u00e1d\u00ed obchodn\u00ed pot\u0159eby do praktick\u00fdch \u0159e\u0161en\u00ed podporuj\u00edc\u00edch projektov\u00e9 t\u00fdmy. M\u00e1 zku\u0161enosti s implementac\u00ed FlexiProject v organizac\u00edch r\u016fzn\u00e9 velikosti a kombinuje technick\u00e9 znalosti s obchodn\u00edm p\u0159\u00edstupem k efektivn\u00edmu pl\u00e1nov\u00e1n\u00ed a realizaci projekt\u016f.","jobTitle":"General Manager at FlexiProject","sameAs":["https:\/\/www.linkedin.com\/in\/dominik-wrzosek-929425140\/"],"image":{"@type":"ImageObject","url":"https:\/\/flexi-project.com\/wp-content\/uploads\/2024\/03\/Dominik-Wrzosek-2.jpg","contentUrl":"https:\/\/flexi-project.com\/wp-content\/uploads\/2024\/03\/Dominik-Wrzosek-2.jpg"}}]}},"_links":{"self":[{"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/posts\/54845","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/users\/10"}],"replies":[{"embeddable":true,"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/comments?post=54845"}],"version-history":[{"count":0,"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/posts\/54845\/revisions"}],"acf:post":[{"embeddable":true,"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/autorzy\/2001"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/media\/54771"}],"wp:attachment":[{"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/media?parent=54845"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/categories?post=54845"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/tags?post=54845"},{"taxonomy":"post_folder","embeddable":true,"href":"https:\/\/flexi-project.com\/cs\/wp-json\/wp\/v2\/post_folder?post=54845"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}